9.000 -- Scope of Part.

This part prescribes policies, standards, and procedures pertaining to prospective contractors’ responsibility; debarment, suspension, and ineligibility; qualified products; first article testing and approval; contractor team arrangements; defense production pools and research and development pools; and organizational conflicts of interest.

Subpart 9.1 -- Responsible Prospective Contractors

9.100 -- Scope of Subpart.

This subpart prescribes policies, standards, and procedures for determining whether prospective contractors and subcontractors are responsible.

9.101 -- Definition.

“Surveying activity,” as used in this subpart, means the cognizant contract administration office or, if there is no such office, another organization designated by the agency to conduct preaward surveys.

9.102 -- Applicability.

(a) This subpart applies to all proposed contracts with any prospective contractor that is located --

(b) This subpart does not apply to proposed contracts with

9.103 -- Policy.

(a) Purchases shall be made from, and contracts shall be awarded to, responsible prospective contractors only.

(b) No purchase or award shall be made unless the contracting officer makes an affirmative determination of responsibility. In the absence of information clearly indicating that the prospective contractor is responsible, the contracting officer shall make a determination of nonresponsibility. If the prospective contractor is a small business concern, the contracting officer shall comply with subpart 19.6, Certificates of Competency and Determinations of Responsibility. (If Section 8(a) of the Small Business Act (15 U.S.C. 637) applies, see Subpart 19.8.)

(c) The award of a contract to a supplier based on lowest evaluated price alone can be false economy if there is subsequent default, late deliveries, or other unsatisfactory performance resulting in additional contractual or administrative costs. While it is important that Government purchases be made at the lowest price, this does not require an award to a supplier solely because that supplier submits the lowest offer. A prospective contractor must affirmatively demonstrate its responsibility, including, when necessary, the responsibility of its proposed subcontractors.

9.104 -- Standards.

9.104-1 -- General Standards.

To be determined responsible, a prospective contractor must --

(a) Have adequate financial resources to perform the contract, or the ability to obtain them (see 9.104-3(a));

(b) Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments;

(c) Have a satisfactory performance record (see 9.104-3(b) and Subpart 42.15). A prospective contractor shall not be determined responsible or nonresponsible solely on the basis of a lack of relevant performance history, except as provided in 9.104-2;

(d) Have a satisfactory record of integrity and business ethics;

(e) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors). (See 9.104-3 (a).)

(f) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them (see 9.104-3(a)); and

(g) Be otherwise qualified and eligible to receive an award under applicable laws and regulations.

9.104-2 -- Special Standards.

(a) When it is necessary for a particular acquisition or class of acquisitions, the contracting officer shall develop, with the assistance of appropriate specialists, special standards of responsibility. Special standards may be particularly desirable when experience has demonstrated that unusual expertise or specialized facilities are needed for adequate contract performance. The special standards shall be set forth in the solicitation (and so identified) and shall apply to all offerors.

(b) Contracting officers shall award contracts for subsistence only to those prospective contractors that meet the general standards in 9.104-1 and are approved in accordance with agency sanitation standards and procedures.

9.104-3 -- Application of Standards.

9.104-4 -- Subcontractor Responsibility.

(a) Generally, prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors (but see 9.405 and 9.405-2 regarding debarred, ineligible, or suspended firms). Determinations of prospective subcontractor responsibility may affect the Government’s determination of the prospective prime contractor’s responsibility. A prospective contractor may be required to provide written evidence of a proposed subcontractor’s responsibility.

(b) When it is in the Government’s interest to do so, the contracting officer may directly determine a prospective subcontractor’s responsibility (e.g., when the prospective contract involves medical supplies, urgent requirements, or substantial subcontracting). In this case, the same standards used to determine a prime contractor’s responsibility shall be used by the Government to determine subcontractor responsibility.

9.105 -- Procedures.

9.105-1 -- Obtaining Information.

(a) Before making a determination of responsibility, the contracting officer shall possess or obtain information sufficient to be satisfied that a prospective contractor currently meets the applicable standards in 9.104.

(b)

(c) In making the determination of responsibility (see 9.104-1(c)), the contracting officer shall consider relevant past performance information (see Subpart 42.15). In addition, the contracting officer should use the following sources of information to support such determinations:

(d) Contracting offices and cognizant contract administration offices that become aware of circumstances casting doubt on a contractor's ability to perform contracts successfully shall promptly exchange relevant information.

9.105-2 -- Determinations and Documentation.

(a) Determinations.

(b) Support documentation. Documents and reports supporting a determination of responsibility or nonresponsibility, including any preaward survey reports and any applicable Certificate of Competency, must be included in the contract file.

9.105-3 -- Disclosure of Preaward Information.

(a) Except as provided in Subpart 24.2, Freedom of Information Act, information (including the preaward survey report) accumulated for purposes of determining the responsibility of a prospective contractor shall not be released or disclosed outside the Government.

(b) The contracting officer may discuss preaward survey information with the prospective contractor before determining responsibility. After award, the contracting officer or, if it is appropriate, the head of the surveying activity or a designee may discuss the findings of the preaward survey with the company surveyed.

(c) Preaward survey information may contain proprietary or source selection information and should be marked with the appropriate legend and protected accordingly (see 3.104-4).

9.106 -- Preaward Surveys.

9.106-1 -- Conditions for Preaward Surveys.

(a) A preaward survey is normally required only when the information on hand or readily available to the contracting officer, including information from commercial sources, is not sufficient to make a determination regarding responsibility. In addition, if the contemplated contract will have a fixed price at or below the simplified acquisition threshold or will involve the acquisition of commercial items (see Part 12), the contracting officer should not request a preaward survey unless circumstances justify its cost.

(b) When a cognizant contract administration office becomes aware of a prospective award to a contractor about which unfavorable information exists and no preaward survey has been requested, it shall promptly obtain and transmit details to the contracting officer.

(c) Before beginning a preaward survey, the surveying activity shall ascertain whether the prospective contractor is debarred, suspended, or ineligible (see Subpart 9.4). If the prospective contractor is debarred, suspended, or ineligible, the surveying activity shall advise the contracting officer promptly and not proceed with the preaward survey unless specifically requested to do so by the contracting officer.

9.106-2 -- Requests for Preaward Surveys.

The contracting officer’s request to the surveying activity (Preaward Survey of Prospective Contractor (General), SF 1403) shall --

(a) Identify additional factors about which information is needed;

(b) Include the complete solicitation package (unless it has previously been furnished), and any information indicating prior unsatisfactory performance by the prospective contractor;

(c) State whether the contracting office will participate in the survey;

(d) Specify the date by which the report is required. This date should be consistent with the scope of the survey requested and normally shall allow at least 7 working days to conduct the survey; and

(e) When appropriate, limit the scope of the survey.

9.106-3 -- Interagency Preaward Surveys.

When the contracting office and the surveying activity are in different agencies, the procedures of this section 9.106 and Subpart 42.1 shall be followed along with the regulations of the agency in which the surveying activity is located, except that reasonable special requests by the contracting office shall be accommodated.

9.106-4 -- Reports.

(a) The surveying activity shall complete the applicable parts of SF 1403, Preaward Survey of Prospective Contractor (General); SF 1404, Preaward Survey of Prospective Contractor -- Technical; SF 1405, Preaward Survey of Prospective Contractor -- Production; SF 1406, Preaward Survey of Prospective Contractor -- Quality Assurance; SF 1407, Preaward Survey of Prospective Contractor -- Financial Capability; and SF 1408, Preaward Survey of Prospective Contractor -- Accounting System; and provide a narrative discussion sufficient to support both the evaluation ratings and the recommendations.

(b) When the contractor surveyed is a small business that has received preferential treatment on an ongoing contract under Section 8(a) of the Small Business Act (15 U.S.C. 637) or has received a Certificate of Competency during the last 12 months, the surveying activity shall consult the appropriate Small Business Administration field office before making an affirmative recommendation regarding the contractor’s responsibility or nonresponsibility.

(c) When a preaward survey discloses previous unsatisfactory performance, the surveying activity shall specify the extent to which the prospective contractor plans, or has taken, corrective action. Lack of evidence that past failure to meet contractual requirements was the prospective contractor’s fault does not necessarily indicate satisfactory performance. The narrative shall report any persistent pattern of need for costly and burdensome Government assistance (e.g., engineering, inspection, or testing) provided in the Government’s interest but not contractually required.

(d) When the surveying activity possesses information that supports a recommendation of complete award without an on-site survey and no special areas for investigation have been requested, the surveying activity may provide a short-form preaward survey report. The short-form report shall consist solely of the Preaward Survey of Prospective Contractor (General), SF 1403. Sections III and IV of this form shall be completed and block 21 shall be checked to show that the report is a short-form preaward report.

9.107 -- Surveys of Nonprofit Agencies Serving People who are Blind or Have Other Severe Disabilities Under the Javits-Wagner-O Day (JWOD) Program.

(a) The Committee for Purchase From People Who Are Blind or Severely Disabled (Committee), as authorized by 41 U.S.C.46-48c, determines what supplies and services Federal agencies are required to purchase from JWOD participating nonprofit agencies serving people who are blind or have other severe disabilities (see Subpart 8.7). The Committee is required to find a JWOD participating nonprofit agency capable of furnishing the supplies or services before the nonprofit agency can be designated as a mandatory source under the JWOD Program. The Committee may request a contracting office to assist in assessing the capabilities of a nonprofit agency.

(b) The contracting office, upon request from the Committee, shall request a capability survey from the activity responsible for performing preaward surveys, or notify the Committee that the JWOD participating nonprofit agency is capable, with supporting rationale, and that the survey is waived. The capability survey will focus on the technical and production capabilities and applicable preaward survey elements to furnish specific supplies or services being considered for addition to the Procurement List.

(c) The contracting office shall use the Standard Form 1403 to request a capability survey of organizations employing people who are blind or have other severe disabilities.

(d) The contracting office shall furnish a copy of the completed survey, or notice that the JWOD participating nonprofit agency is capable and the survey is waived, to the Executive Director, Committee for Purchase From People Who Are Blind or Severely Disabled.

Subpart 9.2 -- Qualifications Requirements

9.200 -- Scope of Subpart.

This subpart implements 10 U.S.C. 2319 and 41 U.S.C. 253c and prescribes policies and procedures regarding qualification requirements and the acquisitions that are subject to such requirements.

9.201 -- Definitions.

As used in this subpart--

“Qualified bidders list (QBL)” means a list of bidders who have had their products examined and tested and who have satisfied all applicable qualification requirements for that product or have otherwise satisfied all applicable qualification requirements.

“Qualified manufacturers list (QML)” means a list of manufacturers who have had their products examined and tested and who have satisfied all applicable qualification requirements for that product.

9.202 -- Policy.

(a)

(b) When justified under the circumstances, the agency activity responsible for establishing a qualification requirement shall submit to the competition advocate for the procuring activity responsible for purchasing the item subject to the qualification requirement, a determination that it is unreasonable to specify the standards for qualification which a prospective offeror (or its product) must satisfy. After considering any comments of the competition advocate reviewing the determination, the head of the procuring activity may waive the requirements of 9.202(a)(1)(ii) through (4) above for up to 2 years with respect to the item subject to the qualification requirement. A copy of the waiver shall be furnished to the head of the agency or other official responsible for actions under 9.202(a)(1). The waiver authority provided in this paragraph does not apply with respect to qualification requirements contained in a QPL, QML, or QBL.

(c) If a potential offeror can demonstrate to the satisfaction of the contracting officer that the potential offeror (or its product) meets the standards established for qualification or can meet them before the date specified for award of the contract, a potential offeror may not be denied the opportunity to submit and have considered an offer for a contract solely because the potential offeror --

(d) The procedures in Subpart 19.6 for referring matters to the Small Business Administration are not mandatory on the contracting officer when the basis for a referral would involve a challenge by the offeror to either the validity of the qualification requirement or the offeror’s compliance with such requirement.

(e) The contracting officer need not delay a proposed award in order to provide a potential offeror with an opportunity to demonstrate its ability to meet the standards specified for qualification. In addition, when approved by the head of an agency or designee, a procurement need not be delayed in order to comply with 9.202(a).

(f) Within 7 years following enforcement of a QPL, QML, or QBL by DOD or NASA, or within 7 years after any qualification requirement was originally established by a civilian agency other than NASA, the qualification requirement shall be examined and revalidated in accordance with the requirements of 9.202(a). For DOD and NASA, qualification requirements other than QPL’s, QML’s and QBL’s shall be examined and revalidated within 7 years after establishment of the requirement under 9.202(a). Any periods for which a waiver under 9.202(b) is in effect shall be excluded in computing the 7 years within which review and revalidation must occur.

9.203 -- QPLs, QMLs, and QBLs.

(a) Qualification and listing in a QPL, QML, or QBL is the process by which products are obtained from manufacturers or distributors, examined and tested for compliance with specification requirements, or manufacturers or potential offerors, are provided an opportunity to demonstrate their abilities to meet the standards specified for qualification. The names of successful products, manufacturers, or potential offerors are included on lists evidencing their status. Generally, qualification is performed in advance and independently of any specific acquisition action. After qualification, the products, manufacturers, or potential offerors are included in a Federal or Military QPL, QML, or QBL. (See 9.202(a)(2) with regard to any product, manufacturer, or potential offeror not yet included on an applicable list.)

(b) Specifications requiring a qualified product are included in the following publications:

(c) Instructions concerning qualification procedures are included in the following publications:

(d) The publications listed in paragraphs (b) and (c) of this section are sold to the public. The publications in paragraphs (b)(1) and (c)(1) of this section may be obtained from the addressee in 11.201(d)(1). The publications in paragraphs (b)(2) and (c)(2) of this section may be obtained from the addressee in 11.201(d)(2).

9.204 -- Responsibilities for Establishment of a Qualification Requirement.

The responsibilities of agency activities that establish qualification requirements include the following:

(a) Arranging publicity for the qualification requirements. If active competition on anticipated future qualification requirements is likely to be fewer than two manufacturers or the products of two manufacturers, the activity responsible for establishment of the qualification requirements must --

(b) Qualifying products that meet specification requirements.

(c) Listing manufacturers and suppliers whose products are qualified in accordance with agency procedures.

(d) Furnishing QPL’s, QML’s, or QBL’s or the qualification requirements themselves to prospective offerors and the public upon request (see 9.202(a)(2)(i) above).

(e) Clarifying, as necessary, qualification requirements.

(f) In appropriate cases, when requested by the contracting officer, providing concurrence in a decision not to enforce a qualification requirement for a solicitation.

(g) Withdrawing or omitting qualification of a listed product, manufacturer or offeror, as necessary.

(h) Advising persons furnished any list of products, manufacturers or offerors meeting a qualification requirement and suppliers whose products are on any such list that --

(i) Reexamining a qualified product or manufacturer when --

9.205 -- Opportunity for Qualification Before Award.

(a) If an agency determines that a qualification requirement is necessary, the agency activity responsible for establishing the requirement must urge manufacturers and other potential sources to demonstrate their ability to meet the standards specified for qualification and, when possible, give sufficient time to arrange for qualification before award. The responsible agency activity must, before establishing any qualification requirement, furnish notice through the GPE. The notice must include--

(b) The activity responsible for establishing a qualification requirement must keep any list maintained of those already qualified open for inclusion of additional products, manufacturers, or other potential sources.

9.206 -- Acquisitions Subject to Qualification Requirements.

9.206-1 -- General.

(a) Agencies may not enforce any QPL, QML, or QBL without first complying with the requirements of 9.202(a). However, qualification requirements themselves, whether or not previously embodied in a in a QPL, QML, or QBL, may be enforced without regard to 9.202 (a) if they are in either of the following categories:

(b) Except when the agency head or designee determines that an emergency exists, whenever an agency elects, whether before or after award, not to enforce a qualification requirement which it established, the requirement may not thereafter be enforced unless the agency complies with 9.202(a).

(c) If a qualification requirement applies, the contracting officer need consider only those offers identified as meeting the requirement or included on the applicable QPL, QML, or QBL, unless an offeror can satisfactorily demonstrate to the contracting officer that it or its product or its subcontractor or its product can meet the standards established for qualification before the date specified for award.

(d) If a product subject to a qualification requirement is to be acquired as a component of an end item, the contracting officer must ensure that all such components and their qualification requirements are properly identified in the solicitation since the product or source must meet the standards specified for qualification before award.

(e) In acquisitions subject to qualification requirements, the contracting officer shall take the following steps:

9.206-2 -- Contract Clause.

The contracting officer shall insert the clause at 52.209-1, Qualification Requirements, in solicitations and contracts when the acquisition is subject to a qualification requirement.

9.206-3 -- Competition.

(a) Presolicitation. If a qualification requirement applies to an acquisition, the contracting officer shall review the applicable QPL, QML, or QBL or other identification of those sources which have met the requirement before issuing a solicitation to ascertain whether the number of sources is adequate for competition. (See 9.204(a) for duties of the agency activity responsible for establishment of the qualification requirement.) If the number of sources is inadequate, the contracting officer shall request the agency activity which established the requirement to --

(b) Post solicitation. The contracting officer shall submit to the agency activity which established the qualification requirement the names and addresses of concerns which expressed interest in the acquisition but are not included on the applicable QPL, QML, or QBL or identified as meeting the qualification requirement. The activity will then assist interested concerns in meeting the standards specified for qualification (see 9.202(a)(2) and (4)).

9.207 -- Changes in Status Regarding Qualification Requirements.

(a) The contracting officer shall promptly report to the agency activity which established the qualification requirement any conditions which may merit removal or omission from a QPL, QML, or QBL or affect whether a source should continue to be otherwise identified as meeting the requirement. These conditions exist when --

(b) After considering any of the above or other conditions reasonably related to whether a product or source continues to meet the standards specified for qualification, an agency may take appropriate action without advance notification. The agency shall, however, promptly notify the affected parties if a product or source is removed from a QPL, QML, or QBL, or will no longer be identified as meeting the standards specified for qualification. This notice shall contain specific information why the product or source no longer meets the qualification requirement.

Subpart 9.3 -- First Article Testing and Approval

9.301 -- Definition.

“Approval,” as used in this subpart, means the contracting officer’s written notification to the contractor accepting the test results of the first article.

9.302 -- General.

First article testing and approval (hereafter referred to as testing and approval) ensures that the contractor can furnish a product that conforms to all contract requirements for acceptance. Before requiring testing and approval, the contracting officer shall consider the --

(a) Impact on cost or time of delivery;

(b) Risk to the Government of foregoing such test; and

(c) Availability of other, less costly, methods of ensuring the desired quality.

9.303 -- Use.

Testing and approval may be appropriate when --

(a) The contractor has not previously furnished the product to the Government;

(b) The contractor previously furnished the product to the Government, but --

(c) The product is described by a performance specification; or

(d) It is essential to have an approved first article to serve as a manufacturing standard.

9.304 -- Exceptions.

Normally, testing and approval is not required in contracts for --

(a) Research or development;

(b) Products requiring qualification before award (e.g., when an applicable qualified products list exists (see Subpart 9.2));

(c) Products normally sold in the commercial market; or

(d) Products covered by complete and detailed technical specifications, unless the requirements are so novel or exacting that it is questionable whether the products would meet the requirements without testing and approval.

9.305 -- Risk.

Before first article approval, the acquisition of materials or components, or commencement of production, is normally at the sole risk of the contractor. To minimize this risk, the contracting officer shall provide sufficient time in the delivery schedule for acquisition of materials and components, and for production after receipt of first article approval. When Government requirements preclude this action, the contracting officer may, before approval of the first article, authorize the contractor to acquire specific materials or components or commence production to the extent essential to meet the delivery schedule (see Alternate II of the clause at 52.209-3, First Article Approval -- Contractor Testing, and Alternate II of the clause at 52.209-4, First Article Approval -- Government Testing). Costs incurred based on this authorization are allocable to the contract for --

9.306 -- Solicitation Requirements.

Solicitations containing a testing and approval requirement shall --

(a) Provide, in the circumstance where the contractor is to be responsible for the first article approval testing --

(b) Provide, in the circumstance where the Government is to be responsible for the first article approval testing --

(c) Inform offerors that the requirement may be waived when supplies identical or similar to those called for have previously been delivered by the offeror and accepted by the Government (see 52.209-3(h) and 52.209-4(i));

(d) Permit the submission of alternative offers, one including testing and approval and the other excluding testing and approval (if eligible under 9.306(c));

(e) State clearly the first article’s relationship to the contract quantity (see paragraph (e) of the clause at 52.209-3, First Article Approval -- Contractor Testing, or 52.209-4, First Article Approval -- Government Testing);

(f) Contain a delivery schedule for the production quantity (see 12.104). The delivery schedule may --

(g) Provide for the submission of contract numbers, if any, to document the offeror’s eligibility under 9.306(c);

(h) State whether the approved first article will serve as a manufacturing standard; and

(i) Include, when the Government is responsible for first article testing, the Government’s estimated testing costs as a factor for use in evaluating offers (when appropriate).

(j) Inform offerors that the prices for first articles and first article tests in relation to production quantities shall not be materially unbalanced (see 15.404-1(g)) if first article test items or tests are to be separately priced.

9.307 -- Government Administration Procedures.

(a) Before the contractor ships the first article, or the first article test report, to the Government laboratory or other activity responsible for approval at the address specified in the contract, the contract administration office shall provide that activity with as much advance notification as is feasible of the forthcoming shipment, and --

(b) The Government laboratory or other activity responsible for first article testing or evaluation shall inform the contracting office whether to approve, conditionally approve, or disapprove the first article. The contracting officer shall then notify the contractor of the action taken and furnish a copy of the notice to the contract administration office. The notice shall include the first article shipment number, when available, and the applicable contract line item number. Any changes in the drawings, designs, or specifications determined by the contracting officer to be necessary shall be made under the Changes clause, and not by the notice of approval, conditional approval, or disapproval furnished the contractor.

9.308 -- Contract Clauses.

9.308-1 -- Testing Performed by the Contractor.

(a)

(b)

9.308-2 -- Testing Performed by the Government.

(a)

(b)

Subpart 9.4 -- Debarment, Suspension, and Ineligibility

9.400 -- Scope of Subpart.

(a) This subpart --

(b) Although this subpart does cover the listing of ineligible contractors (9.404) and the effect of this listing (9.405(b)), it does not prescribe policies and procedures governing declarations of ineligibility.

9.401 -- Applicability.

In accordance with Public Law 103-355, Section 2455 (31 U.S.C.6101, note), and Executive Order 12689, any debarment, suspension or other Governmentwide exclusion initiated under the Nonprocurement Common Rule implementing Executive Order 12549 on or after August 25, 1995, shall be recognized by and effective for Executive Branch agencies as a debarment or suspension under this subpart. Similarly, any debarment, suspension, proposed debarment or other Governmentwide exclusion initiated on or after August 25, 1995, under this subpart shall also be recognized by and effective for those agencies and participants as an exclusion under the Nonprocurement Common Rule.

9.402 -- Policy.

(a) Agencies shall solicit offers from, award contracts to, and consent to subcontracts with responsible contractors only. Debarment and suspension are discretionary actions that, taken in accordance with this subpart, are appropriate means to effectuate this policy.

(b) The serious nature of debarment and suspension requires that these sanctions be imposed only in the public interest for the Government’s protection and not for purposes of punishment. Agencies shall impose debarment or suspension to protect the Government’s interest and only for the causes and in accordance with the procedures set forth in this subpart.

(c) When more than one agency has an interest in the debarment or suspension of a contractor, consideration shall be given to designating one agency as the lead agency for making the decision. Agencies are encouraged to establish methods and procedures for coordinating their debarment or suspension actions.

(d) Agencies shall establish appropriate procedures to implement the policies and procedures of this subpart.

9.403 -- Definitions.

As used in this subpart--

“Affiliates.” Business concerns, organizations, or individuals are affiliates of each other if, directly or indirectly,

“Agency” means any executive department, military department or defense agency, or other agency or independent establishment of the executive branch.

“Civil judgment” means a judgment or finding of a civil offense by any court of competent jurisdiction.

“Contractor” means any individual or other legal entity that --

“Debarring official” means--

“Indictment” means indictment for a criminal offense. An information or other filing by competent authority charging a criminal offense is given the same effect as an indictment.

“Legal proceedings” means any civil judicial proceeding to which the Government is a party or any criminal proceeding. The term includes appeals from such proceedings.

“Nonprocurement Common Rule” means the procedures used by Federal Executive Agencies to suspend, debar, or exclude individuals or entities from participation in nonprocurement transactions under Executive Order 12549. Examples of nonprocurement transactions are grants, cooperative agreements, scholarships, fellowships, contracts of assistance, loans, loan guarantees, subsidies, insurance, payments for specified use, and donation agreements.

“Suspending official” means--

“Unfair trade practices” means the commission of any or the following acts by a contractor:

9.404 -- Excluded Parties List System.

(a) The General Services Administration (GSA) --

(b) The EPLS includes the --

(c) Each agency must --

(d) The EPLS is available at http://epls.gov .

9.405 -- Effect of Listing.

(a) Contractors debarred, suspended, or proposed for debarment are excluded from receiving contracts, and agencies shall not solicit offers from, award contracts to, or consent to subcontracts with these contractors, unless the agency head determines that there is a compelling reason for such action (see 9.405-1(b), 9.405-2, 9.406-1(c), 9.407-1(d), and 23.506(e)). Contractors debarred, suspended or proposed for debarment are also excluded from conducting business with the Government as agents or representatives of other contractors.

(b) Contractors included in the EPLS as having been declared ineligible on the basis of statutory or other regulatory procedures are excluded from receiving contracts, and if applicable, subcontracts, under the conditions and for the period set forth in the statute or regulation. Agencies shall not solicit offers from, award contracts to, or consent to subcontracts with these contractors under those conditions and for that period.

(c) Contractors debarred, suspended, or proposed for debarment are excluded from acting as individual sureties (see Part 28).

(d)

9.405-1 -- Continuation of Current Contracts.

9.405-2 -- Restrictions on Subcontracting.

(a) When a contractor debarred, suspended, or proposed for debarment is proposed as a subcontractor for any subcontract subject to Government consent (see Subpart 44.2), contracting officers shall not consent to subcontracts with such contractors unless the agency head states in writing the compelling reasons for this approval action. (See 9.405(b) concerning declarations of ineligibility affecting subcontracting.)

(b) The Government suspends or debars contractors to protect the Government’s interests. By operation of the clause at 52.209-6, Protecting the Government’s Interests When Subcontracting with Contractors Debarred, Suspended or Proposed for Debarment, contractors shall not enter into any subcontract in excess of $25,000 with a contractor that has been debarred, suspended, or proposed for debarment unless there is a compelling reason to do so. If a contractor intends to subcontract with a party that is debarred, suspended, or proposed for debarment as evidenced by the parties’ inclusion in the EPLS (see 9.404), a corporate officer or designee of the contractor is required by operation of the clause at 52.209-6, Protecting the Government’s Interests when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment, to notify the contracting officer, in writing, before entering into such subcontract. The notice must provide the following:

(c) The contractor’s compliance with the requirements of 52.209-6 will be reviewed during Contractor Purchasing System Reviews (see Subpart 44.3).

9.406 -- Debarment.

9.406-1 -- General.

(a) It is the debarring official’s responsibility to determine whether debarment is in the Government’s interest. The debarring official may, in the public interest, debar a contractor for any of the causes in 9.406-2, using the procedures in 9.406-3. The existence of a cause for debarment, however, does not necessarily require that the contractor be debarred; the seriousness of the contractor’s acts or omissions and any remedial measures or mitigating factors should be considered in making any debarment decision. Before arriving at any debarment decision, the debarring official should consider factors such as the following:

The existence or nonexistence of any mitigating factors or remedial measures such as set forth in this paragraph (a) is not necessarily determinative of a contractor’s present responsibility. Accordingly, if a cause for debarment exists, the contractor has the burden of demonstrating, to the satisfaction of the debarring official, its present responsibility and that debarment is not necessary.

(b) Debarment constitutes debarment of all divisions or other organizational elements of the contractor, unless the debarment decision is limited by its terms to specific divisions, organizational elements, or commodities. The debarring official may extend the debarment decision to include any affiliates of the contractor if they are --

(c) A contractor’s debarment, or proposed debarment, shall be effective throughout the executive branch of the Government, unless the agency head or a designee (except see 23.506(e)) states in writing the compelling reasons justifying continued business dealings between that agency and the contractor.

(d)

9.406-2 -- Causes for Debarment.

The debarring official may debar—

(a) A contractor for a conviction of or civil judgment for --

(b)

(c) A contractor or subcontractor based on any other cause of so serious or compelling a nature that it affects the present responsibility the contractor or subcontractor.

9.406-3 -- Procedures.

(a) Investigation and referral. Agencies shall establish procedures for the prompt reporting, investigation, and referral to the debarring official of matters appropriate for that official’s consideration.

(b) Decisionmaking process.

(c) Notice of proposal to debar. A notice of proposed debarment shall be issued by the debarring official advising the contractor and any specifically named affiliates, by certified mail, return receipt requested --

(d) Debarring official’s decision.

(e) Notice of debarring official’s decision.

9.406-4 -- Period of Debarment.

(a)

(b) The debarring official may extend the debarment for an additional period, if that official determines that an extension is necessary to protect the Government’s interest. However, a debarment may not be extended solely on the basis of the facts and circumstances upon which the initial debarment action was based. Debarments under 9.406-2(b)(2) may be extended for additional periods of one year if the Secretary of Homeland Security or the Attorney General determines that the contractor continues to be in violation of the employment provisions of the Immigration and Nationality Act. If debarment for an additional period is determined to be necessary, the procedures of 9.406-3 shall be followed to extend the debarment.

(c) The debarring official may reduce the period or extent of debarment, upon the contractor’s request, supported by documentation, for reasons such as --

9.406-5 -- Scope of Debarment.

(a) The fraudulent, criminal, or other seriously improper conduct of any officer, director, shareholder, partner, employee, or other individual associated with a contractor may be imputed to the contractor when the conduct occurred in connection with the individual’s performance of duties for or on behalf of the contractor, or with the contractor’s knowledge, approval, or acquiescence. The contractor’s acceptance of the benefits derived from the conduct shall be evidence of such knowledge, approval, or acquiescence.

(b) The fraudulent, criminal, or other seriously improper conduct of a contractor may be imputed to any officer, director, shareholder, partner, employee, or other individual associated with the contractor who participated in, knew of, or had reason to know of the contractor’s conduct.

(c) The fraudulent, criminal, or other seriously improper conduct of one contractor participating in a joint venture or similar arrangement may be imputed to other participating contractors if the conduct occurred for or on behalf of the joint venture or similar arrangement, or with the knowledge, approval, or acquiescence of these contractors. Acceptance of the benefits derived from the conduct shall be evidence of such knowledge, approval, or acquiescence.

9.407 -- Suspension.

9.407-1 -- General.

(a) The suspending official may, in the public interest, suspend a contractor for any of the causes in 9.407-2, using the procedures in 9.407-3.

(b)

(c) Suspension constitutes suspension of all divisions or other organizational elements of the contractor, unless the suspension decision is limited by its terms to specific divisions, organizational elements, or commodities. The suspending official may extend the suspension decision to include any affiliates of the contractor if they are --

(d) A contractor’s suspension shall be effective throughout the executive branch of the Government, unless the agency head or a designee (except see 23.506(e)) states in writing the compelling reasons justifying continued business dealings between that agency and the contractor.

(e)

9.407-2 -- Causes for Suspension.

(a) The suspending official may suspend a contractor suspected, upon adequate evidence, of --

(b) Indictment for any of the causes in paragraph (a) above constitutes adequate evidence for suspension.

(c) The suspending official may upon adequate evidence also suspend a contractor for any other cause of so serious or compelling a nature that it affects the present responsibility of a Government contractor or subcontractor.

9.407-3 -- Procedures.

(a) Investigation and referral. Agencies shall establish procedures for the prompt reporting, investigation, and referral to the suspending official of matters appropriate for that official’s consideration.

(b) Decisionmaking process.

(c) Notice of suspension. When a contractor and any specifically named affiliates are suspended, they shall be immediately advised by certified mail, return receipt requested --

(d) Suspending official’s decision.

9.407-4 -- Period of Suspension.

(a) Suspension shall be for a temporary period pending the completion of investigation and any ensuing legal proceedings, unless sooner terminated by the suspending official or as provided in this subsection.

(b) If legal proceedings are not initiated within 12 months after the date of the suspension notice, the suspension shall be terminated unless an Assistant Attorney General requests its extension, in which case it may be extended for an additional 6 months. In no event may a suspension extend beyond 18 months, unless legal proceedings have been initiated within that period.

(c) The suspending official shall notify the Department of Justice of the proposed termination of the suspension, at least 30 days before the 12-month period expires, to give that Department an opportunity to request an extension.

9.407-5 -- Scope of Suspension.

The scope of suspension shall be the same as that for debarment (see 9.406-5), except that the procedures of 9.407-3 shall be used in imposing suspension.

9.408 -- Certification Regarding Debarment, Suspension, Proposed Debarment, and Other Responsibility Matters.

(a) When an offeror, in compliance with the provision at 52.209-5, Certification Regarding Debarment, Suspension, Proposed Debarment, and Other Responsibility Matters, indicates an indictment, charge, civil judgment, conviction, suspension, debarment, proposed debarment, ineligibility, or default of a contract, the contracting officer shall --

(b) Offerors who do not furnish the certification or such information as may be requested by the contracting officer shall be given an opportunity to remedy the deficiency. Failure to furnish the certification or such information may render the offeror nonresponsible.

9.409 -- Solicitation Provision and Contract Clause.

(a) The contracting officer shall insert the provision at 52.209-5, Certification Regarding Debarment, Suspension, Proposed Debarment, and Other Responsibility Matters, in solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(b) The contracting officer shall insert the clause at 52.209-6, Protecting the Government’s Interests when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment, in solicitations and contracts where the contract value exceeds $25,000.

Subpart 9.5 -- Organizational and Consultant Conflicts of Interest

9.500 -- Scope of Subpart.

This subpart --

(a) Prescribes responsibilities, general rules, and procedures for identifying, evaluating, and resolving organizational conflicts of interest;

(b) Provides examples to assist contracting officers in applying these rules and procedures to individual contracting situations; and

(c) Implements section 8141 of the 1989 Department of Defense Appropriation Act, Pub. L. 100-463, 102 Stat. 2270-47 (1988).

9.501 -- Definition.

“Marketing consultant,” as used in this subpart, means any independent contractor who furnishes advice, information, direction, or assistance to an offeror