FAR - Part 31 Contract Cost Principles and Procedures
- Subpart 31.1 -- Applicability
- 31.100 -- Scope of Subpart.
- 31.101 -- Objectives.
- 31.102 -- Fixed-Price Contracts.
- 31.103 -- Contracts with Commercial Organizations.
- 31.104 -- Contracts With Educational Institutions.
- 31.105 -- Construction and Architect-Engineer Contracts.
- 31.106 -- Facilities Contracts.
- 31.106-1 -- Applicable Cost Principles.
- 31.106-2 -- Exceptions to General Rules on Allowability and Allocability.
- 31.106-3 -- Contractors Commercial Items.
- 31.107 -- Contracts With State, Local, and Federally Recognized Indian Tribal Governments.
- 31.108 -- Contracts with Nonprofit Organizations.
- 31.109 -- Advance Agreements.
- 31.110 -- Indirect Cost Rate Certification and Penalties on Unallowable Costs.
- Subpart 31.2 -- Contracts With Commercial Organizations
- 31.201 -- General.
- 31.201-1 -- Composition of Total Cost.
- 31.201-2 -- Determining Allowability.
- 31.201-3 -- Determining Reasonableness.
- 31.201-4 -- Determining Allocability.
- 31.201-5 -- Credits.
- 31.201-6 -- Accounting for Unallowable Costs.
- 31.201-7 -- Construction and Architect-Engineer Contracts.
- 31.202 -- Direct Costs.
- 31.203 -- Indirect Costs.
- 31.204 -- Application of Principles and Procedures.
- 31.205 -- Selected Costs.
- 31.205-1 -- Public Relations and Advertising Costs.
- 31.205-2 -- [Reserved]
- 31.205-3 -- Bad Debts.
- 31.205-4 -- Bonding Costs.
- 31.205-5 – [Reserved].
- 31.205-6 -- Compensation for Personal Services.
- 31.205-7 -- Contingencies.
- 31.205-8 -- Contributions or Donations.
- 31.205-9 -- [Reserved]
- 31.205-10 -- Cost of Money.
- 31.205-11 -- Depreciation.
- 31.205-12 -- Economic Planning Costs.
- 31.205-13 -- Employee Morale, Health, Welfare, Food Service, and Dormitory Costs and Credits.
- 31.205-14 -- Entertainment Costs.
- 31.205-15 -- Fines, Penalties, and Mischarging Costs.
- 31.205-16 -- Gains and Losses on Disposition or Impairment of Depreciable Property or Other Capital Assets.
- 31.205-17 -- Idle Facilities and Idle Capacity Costs.
- 31.205-18 -- Independent Research and Development and Bid and Proposal Costs.
- 31.205-19 -- Insurance and Indemnification.
- 31.205-20 -- Interest and Other Financial Costs.
- (DoD, see Class Deviation below)
- 31.205-21 -- Labor Relations Costs.
- 31.205-22 -- Lobbying and Political Activity Costs.
- 31.205-23 -- Losses on Other Contracts.
- 31.205-24 – [Reserved]
- 31.205-25 -- Manufacturing and Production Engineering Costs.
- 31.205-26 -- Material Costs.
- 31.205-27 -- Organization Costs.
- 31.205-28 -- Other Business Expenses.
- 31.205-29 -- Plant Protection Costs.
- 31.205-30 -- Patent Costs.
- 31.205-31 -- Plant Reconversion Costs.
- 31.205-32 -- Precontract Costs.
- 31.205-33 -- Professional and Consultant Service Costs.
- 31.205-34 -- Recruitment Costs.
- 31.205-35 -- Relocation Costs.
- 31.205-36 -- Rental Costs.
- 31.205-37 -- Royalties and Other Costs for Use of Patents.
- 31.205-38 -- Selling Costs.
- 31.205-39 -- Service and Warranty Costs.
- 31.205-40 -- Special Tooling and Special Test Equipment Costs.
- 31.205-41 -- Taxes.
- 31.205-42 -- Termination Costs.
- 31.205-43 -- Trade, Business, Technical and Professional Activity Costs.
- 31.205-44 -- Training and Education Costs.
- 31.205-45 – [Reserved]
- 31.205-46 -- Travel Costs.
- 31.205-47 -- Costs Related to Legal and Other Proceedings.
- 31.205-48 -- Research and Development Costs.
- 31.205-49 -- Goodwill.
- 31.205-50 -- [Reserved]
- 31.205-51 -- Costs of Alcoholic Beverages.
- 31.205-52 -- Asset Valuations Resulting from Business Combinations.
- Subpart 31.3 -- Contracts With Educational Institutions
- Subparts 31.4 -- 31.5 -- [Reserved]
- Subpart 31.6 -- Contracts with State, Local, and Federally Recognized Indian Tribal Governments
- Subpart 31.7 -- Contracts with Nonprofit Organizations
(FAC 2005-04)
(8 July 2005)
31.000 -- Scope of Part.
This part contains cost principles and procedures for --
(a) The pricing of contracts, subcontracts, and modifications to contracts and subcontracts whenever cost analysis is performed (see 15.404-1); and
(b) The determination, negotiation, or allowance of costs when required by a contract clause.
31.001 -- Definitions.
As used in this part--
“Accrued benefit cost method” means an actuarial cost method under which units of benefit are assigned to each cost accounting period and are valued as they accrue; i.e., based on the services performed by each employee in the period involved. The measure of normal cost under this method for each cost accounting period is the present value of the units of benefit deemed to be credited to employees for service in that period. The measure of the actuarial accrued liability at a plan’s inception date is the present value of the units of benefit credited to employees for service prior to that date. (This method is also known as the unit credit cost method without salary projection.)
“Accumulating costs” means collecting cost data in an organized manner, such as through a system of accounts.
“Actual cash value” means the cost of replacing damaged property with other property of like kind and quality in the physical condition of the property immediately before the damage.
“Actual costs” means (except for Subpart 31.6) amounts determined on the basis of costs incurred, as distinguished from forecasted costs. Actual costs include standard costs properly adjusted for applicable variances.
“Actuarial accrued liability” means pension cost attributable, under the actuarial cost method in use, to years prior to the current period considered by a particular actuarial valuation. As of such date, the actuarial accrued liability represents the excess of the present value of future benefits and administrative expenses over the present value of future normal costs for all plan participants and beneficiaries. The excess of the actuarial accrued liability over the actuarial value of the assets of a pension plan is the unfunded actuarial liability. The excess of the actuarial value of the assets of a pension plan over the actuarial accrued liability is an actuarial surplus and is treated as a negative unfunded actuarial liability.
“Actuarial assumption” means an estimate of future conditions affecting pension cost; e.g., mortality rate, employee turnover, compensation levels, earnings on pension plan assets, and changes in values of pension plan assets.
“Actuarial cost method” means a technique that uses actuarial assumptions to measure the present value of future pension benefits and pension plan administrative expenses, and that assigns the cost of such benefits and expenses to cost accounting periods. The actuarial cost method includes the asset valuation method used to determine the actuarial value of the assets of a pension plan.
“Actuarial gain and loss” means the effect on pension cost resulting from differences between actuarial assumptions and actual experience.
“Actuarial valuation” means the determination, as of a specified date, of the normal cost, actuarial accrued liability, actuarial value of the assets of a pension plan, and other relevant values for the pension plan.
“Allocate” means to assign an item of cost, or a group of items of cost, to one or more cost objectives. This term includes both direct assignment of cost and the reassignment of a share from an indirect cost pool.
“Compensated personal absence” means any absence from work for reasons such as illness, vacation, holidays, jury duty, military training, or personal activities for which an employer pays compensation directly to an employee in accordance with a plan or custom of the employer.
“Compensation for personal services” means all remuneration paid currently or accrued, in whatever form and whether paid immediately or deferred, for services rendered by employees to the contractor.
“Cost input” means the cost, except general and administrative (G&A) expenses, which for contract costing purposes is allocable to the production of goods and services during a cost accounting period.
“Cost objective” means (except for Subpart 31.6) a function, organizational subdivision, contract, or other work unit for which cost data are desired and for which provision is made to accumulate and measure the cost of processes, products, jobs, capitalized projects, etc.
“Deferred compensation” means an award made by an employer to compensate an employee in a future cost accounting period or periods for services rendered in one or more cost accounting periods before the date of the receipt of compensation by the employee. This definition shall not include the amount of year end accruals for salaries, wages, or bonuses that are to be paid within a reasonable period of time after the end of a cost accounting period.
“Defined-benefit pension plan” means a pension plan in which the benefits to be paid, or the basis for determining such benefits, are established in advance and the contributions are intended to provide the stated benefits.
“Defined-contribution pension plan” means a pension plan in which the contributions to be made are established in advance and the benefits are determined thereby.
“Directly associated cost” means any cost which is generated solely as a result of the incurrence of another cost, and which would not have been incurred had the other cost not been incurred.
“Estimating costs” means the process of forecasting a future result in terms of cost, based upon information available at the time.
“Expressly unallowable cost” means a particular item or type of cost which, under the express provisions of an applicable law, regulation, or contract, is specifically named and stated to be unallowable.
“Final cost objective” means (except for Subparts 31.3 and 31.6) a cost objective that has allocated to it both direct and indirect costs and, in the contractor’s accumulation system, is one of the final accumulation points.
“Fiscal year” means the accounting period for which annual financial statements are regularly prepared, generally a period of 12 months, 52 weeks, or 53 weeks.
“Funded pension cost” means the portion of pension cost for a current or prior cost accounting period that has been paid to a funding agency.
“Home office” means an office responsible for directing or managing two or more, but not necessarily all, segments of an organization. It typically establishes policy for, and provides guidance to, the segments in their operations. It usually performs management, supervisory, or administrative functions, and may also perform service functions in support of the operations of the various segments. An organization which has intermediate levels, such as groups, may have several home offices which report to a common home office. An intermediate organization may be both a segment and a home office.
“Immediate-gain actuarial cost method” means any of the several actuarial cost methods under which actuarial gains and losses are included as part of the unfunded actuarial liability of the pension plan, rather than as part of the normal cost of the plan.
“Independent research and development (IR&D) cost” means the cost of effort which is neither sponsored by a grant, nor required in performing a contract, and which falls within any of the following four areas --
(a) Basic research,
(b) Applied research,
(c) Development, and
(d) Systems and other concept formulation studies.
“Indirect cost pools” means (except for Subparts 31.3 and 31.6) groupings of incurred costs identified with two or more cost objectives but not identified specifically with any final cost objective.
“Insurance administration expenses” means the contractor’s costs of administering an insurance program; e.g., the costs of operating an insurance or risk-management department, processing claims, actuarial fees, and service fees paid to insurance companies, trustees, or technical consultants.
“Intangible capital asset” means an asset that has no physical substance, has more than minimal value, and is expected to be held by an enterprise for continued use or possession beyond the current accounting period for the benefits it yields.
“Job” means a homogeneous cluster of work tasks, the completion of which serves an enduring purpose for the organization. Taken as a whole, the collection of tasks, duties, and responsibilities constitutes the assignment for one or more individuals whose work is of the same nature and is performed at the same skill/responsibility level -- as opposed to a position, which is a collection of tasks assigned to a specific individual. Within a job, there may be pay categories which are dependent on the degree of supervision required by the employee while performing assigned tasks which are performed by all persons with the same job.
“Job class of employees” means employees performing in positions within the same job.
“Labor cost at standard” means a preestablished measure of the labor element of cost, computed by multiplying labor-rate standard by labor-time standard.
“Labor market” means a place where individuals exchange their labor for compensation. Labor markets are identified and defined by a combination of the following factors --
(1) Geography,
(2) Education and/or technical background required,
(3) Experience required by the job,
(4) Licensing or certification requirements,
(5) Occupational membership, and
(6) Industry.
“Labor-rate standard” means a preestablished measure, expressed in monetary terms, of the price of labor.
“Labor-time standard” means a preestablished measure, expressed in temporal terms, of the quantity of labor.
“Material cost at standard” means a preestablished measure of the material elements of cost, computed by multiplying material-price standard by material-quantity standard.
“Material-price standard” means a preestablished measure, expressed in monetary terms, of the price of material.
“Material-quantity standard” means a preestablished measure, expressed in physical terms, of the quantity of material.
“Moving average cost” means an inventory costing method under which an average unit cost is computed after each acquisition by adding the cost of the newly acquired units to the cost of the units of inventory on hand and dividing this figure by the new total number of units.
“Nonqualified pension plan” means any pension plan other than a qualified pension plan as defined in this part.
“Normal cost” means the annual cost attributable, under the actuarial cost method in use, to current and future years as of a particular valuation date excluding any payment in respect of an unfunded actuarial liability.
“Original complement of low cost equipment” means a group of items acquired for the initial outfitting of a tangible capital asset or an operational unit, or a new addition to either. The items in the group individually cost less than the minimum amount established by the contractor for capitalization for the classes of assets acquired but in the aggregate they represent a material investment. The group, as a complement, is expected to be held for continued service beyond the current period. Initial outfitting of the unit is completed when the unit is ready and available for normal operations.
“Pay-as-you-go cost method” means a method of recognizing pension cost only when benefits are paid to retired employees or their beneficiaries.
“Pension plan” means a deferred compensation plan established and maintained by one or more employers to provide systematically for the payment of benefits to plan participants after their retirements; provided, that the benefits are paid for life or are payable for life at the option of the employees. Additional benefits such as permanent and total disability and death payments, and survivorship payments to beneficiaries of deceased employees, may be an integral part of a pension plan.
“Pension plan participant” means any employee or former employee of an employer or any member or former member of an employee organization, who is or may become eligible to receive a benefit from a pension plan which covers employees of such employer or members of such organization who have satisfied the plan’s participation requirements, or whose beneficiaries are receiving or may be eligible to receive any such benefit. A participant whose employment status with the employer has not been terminated is an active participant of the employer’s pension plan.
“Profit center” means (except for Subparts 31.3 and 31.6) the smallest organizationally independent segment of a company charged by management with profit and loss responsibilities.
“Projected benefit cost method” means either—
(1) Any of the several actuarial cost methods that distribute the estimated total cost of all the employees’ prospective benefits over a period of years, usually their working careers; or
(2) A modification of the accrued benefit cost method that considers projected compensation levels.
“Proposal” means any offer or other submission used as a basis for pricing a contract, contract modification, or termination settlement or for securing payments thereunder.
“Qualified pension plan” means a pension plan comprising a definite written program communicated to and for the exclusive benefit of employees that meets the criteria deemed essential by the Internal Revenue Service as set forth in the Internal Revenue Code for preferential tax treatment regarding contributions, investments, and distributions. Any other plan is a nonqualified pension plan.
“Self-insurance charge” means a cost which represents the projected average loss under a self-insurance plan.
“Service life” means the period of usefulness of a tangible capital asset (or group of assets) to its current owner. The period may be expressed in units of time or output. The estimated service life of a tangible capital asset (or group of assets) is a current forecast of its service life and is the period over which depreciation cost is to be assigned.
“Spread-gain actuarial cost method” means any of the several projected benefit actuarial cost methods under which actuarial gains and losses are included as part of the current and future normal costs of the pension plan.
“Standard cost” means any cost computed with the use of preestablished measures.
“Tangible capital asset” means an asset that has physical substance, more than minimal value, and is expected to be held by an enterprise for continued use or possession beyond the current accounting period for the services it yields.
“Termination of employment gain or loss” means an actuarial gain or loss resulting from the difference between the assumed and actual rates at which pension plan participants separate from employment for reasons other than retirement, disability, or death.
“Variance” means the difference between a preestablished measure and an actual measure.
“Weighted average cost” means an inventory costing method under which an average unit cost is computed periodically by dividing the sum of the cost of beginning inventory plus the cost of acquisitions by the total number of units included in these two categories.
31.002 -- Availability of Accounting Guide.
Contractors needing assistance in developing or improving their accounting systems and procedures may request a copy of the Defense Contract Audit Agency Pamphlet No. 7641.90, Information for Contractors. The pamphlet is available via the Internet at http://www.dcaa.mil .
Subpart 31.1 -- Applicability
31.100 -- Scope of Subpart.
This subpart describes the applicability of the cost principles and procedures in succeeding subparts of this part to various types of contracts and subcontracts. It also describes the need for advance agreements.
31.101 -- Objectives.
In recognition of differing organizational characteristics, the cost principles and procedures in the succeeding subparts are grouped basically by organizational type; e.g., commercial concerns and educational institutions. The overall objective is to provide that, to the extent practicable, all organizations of similar types doing similar work will follow the same cost principles and procedures. To achieve this uniformity, individual deviations concerning cost principles require advance approval of the agency head or designee. Class deviations for the civilian agencies require advance approval of the Civilian Agency Acquisition Council. Class deviations for the National Aeronautics and Space Administration require advance approval of the Deputy Chief Acquisition Officer. Class deviations for the Department of Defense require advance approval of the Director of Defense Procurement, Office of the Under Secretary of Defense for Acquisition, Technology, and Logistics.
31.102 -- Fixed-Price Contracts.
The applicable subparts of Part 31 shall be used in the pricing of fixed-price contracts, subcontracts, and modifications to contracts and subcontracts whenever
(a) cost analysis is performed, or
(b) a fixed-price contract clause requires the determination or negotiation of costs. However, application of cost principles to fixed-price contracts and subcontracts shall not be construed as a requirement to negotiate agreements on individual elements of cost in arriving at agreement on the total price. The final price accepted by the parties reflects agreement only on the total price. Further, notwithstanding the mandatory use of cost principles, the objective will continue to be to negotiate prices that are fair and reasonable, cost and other factors considered.
31.103 -- Contracts with Commercial Organizations.
This category includes all contracts and contract modifications for supplies, services, or experimental, developmental, or research work negotiated with organizations other than educational institutions (see 31.104), construction and architect-engineer contracts (see 31.105), State and local governments (see 31.107) and nonprofit organizations (see 31.108) on the basis of cost.
(a) The cost principles and procedures in Subpart 31.2 and agency supplements shall be used in pricing negotiated supply, service, experimental, developmental, and research contracts and contract modifications with commercial organizations whenever cost analysis is performed as required by 15.404-1.
(b) In addition, the contracting officer shall incorporate the cost principles and procedures in Subpart 31.2 and agency supplements by reference in contracts with commercial organizations as the basis for --
(1) Determining reimbursable costs under --
(i) Cost-reimbursement contracts and cost-reimbursement subcontracts under these contracts performed by commercial organizations; and
(ii) The cost-reimbursement portion of time-and-materials contracts except when material is priced on a basis other than at cost (see 16.601(b)(3));
(2) Negotiating indirect cost rates (see Subpart 42.7);
(3) Proposing, negotiating, or determining costs under terminated contracts (see 49.103 and 49.113);
(4) Price revision of fixed-price incentive contracts (see 16.204 and 16.403);
(5) Price redetermination of price redetermination contracts (see 16.205 and 16.206); and
(6) Pricing changes and other contract modifications.
31.104 -- Contracts With Educational Institutions.
This category includes all contracts and contract modifications for research and development, training, and other work performed by educational institutions.
(a) The contracting officer shall incorporate the cost principles and procedures in Subpart 31.3 by reference in cost-reimbursement contracts with educational institutions as the basis for --
(1) Determining reimbursable costs under the contracts and cost-reimbursement subcontracts thereunder performed by educational institutions;
(2) Negotiating indirect cost rates; and
(3) Settling costs of cost-reimbursement terminated contracts (see Subpart 49.3 and 49.109-7).
(b) The cost principles in this subpart are to be used as a guide in evaluating costs in connection with negotiating fixed-price contracts and termination settlements.
31.105 -- Construction and Architect-Engineer Contracts.
(a) This category includes all contracts and contract modifications negotiated on the basis of cost with organizations other than educational institutions (see 31.104), State and local governments (see 31.107), and nonprofit organizations except those exempted under OMB Circular A-122 (see 31.108) for construction management or construction, alteration or repair of buildings, bridges, roads, or other kinds of real property. It also includes architect-engineer contracts related to construction projects. It does not include contracts for vessels, aircraft, or other kinds of personal property.
(b) Except as otherwise provided in (d) of this section, the cost principles and procedures in Subpart 31.2 shall be used in the pricing of contracts and contract modifications in this category if cost analysis is performed as required by 15.404-1(c).
(c) In addition, the contracting officer shall incorporate the cost principles and procedures in Subpart 31.2 (as modified by (d) below) by reference in contracts in this category as the basis for --
(1) Determining reimbursable costs under cost-reimbursement contracts, including cost-reimbursement subcontracts thereunder;
(2) Negotiating indirect cost rates;
(3) Proposing, negotiating, or determining costs under terminated contracts;
(4) Price revision of fixed-price incentive contracts; and
(5) Pricing changes and other contract modifications.
(d) Except as otherwise provided in this paragraph (d), the allowability of costs for construction and architect-engineer contracts shall be determined in accordance with Subpart 31.2.
(1) Because of widely varying factors such as the nature, size, duration, and location of the construction project, advance agreements as set forth in 31.109, for such items as home office overhead, partners’ compensation, employment of consultants, and equipment usage costs, are particularly important in construction and architect-engineer contracts. When appropriate, they serve to express the parties’ understanding and avoid possible subsequent disputes or disallowances.
(2) “Construction equipment,” as used in this section, means equipment (including marine equipment) in sound workable condition, either owned or controlled by the contractor or the subcontractor at any tier, or obtained from a commercial rental source, and furnished for use under Government contracts.
(i) Allowable ownership and operating costs shall be determined as follows:
(A) Actual cost data shall be used when such data can be determined for both ownership and operations costs for each piece of equipment, or groups of similar serial or series equipment, from the contractor’s accounting records. When such costs cannot be so determined, the contracting agency may specify the use of a particular schedule of predetermined rates or any part thereof to determine ownership and operating costs of construction equipment (see subdivisions (d)(2)(i)(B) and (C) of this section). However, costs otherwise unallowable under this part shall not become allowable through the use of any schedule (see 31.109(c)). For example, schedules need to be adjusted for Government contract costing purposes if they are based on replacement cost, include unallowable interest costs, or use improper cost of money rates or computations. Contracting officers should review the computations and factors included within the specified schedule and ensure that unallowable or unacceptably computed factors are not allowed in cost submissions.
(B) Predetermined schedules of construction equipment use rates (e.g., the Construction Equipment Ownership and Operating Expense Schedule, published by the U.S. Army Corps of Engineers, industry sponsored construction equipment cost guides, or commercially published schedules of construction equipment use cost) provide average ownership and operating rates for construction equipment. The allowance for operating costs may include costs for such items as fuel, filters, oil, and grease; servicing, repairs, and maintenance; and tire wear and repair. Costs of labor, mobilization, demobilization, overhead, and profit are generally not reflected in schedules, and separate consideration may be necessary.
(C) When a schedule of predetermined use rates for construction equipment is used to determine direct costs, all costs of equipment that are included in the cost allowances provided by the schedule shall be identified and eliminated from the contractor’s other direct and indirect costs charged to the contract. If the contractor’s accounting system provides for site or home office overhead allocations, all costs which are included in the equipment allowances may need to be included in any cost input base before computing the contractor’s overhead rate. In periods of suspension of work pursuant to a contract clause, the allowance for equipment ownership shall not exceed an amount for standby cost as determined by the schedule or contract provision.
(ii) Reasonable costs of renting construction equipment are allowable (but see paragraph (C) of this subsection).
(A) Costs, such as maintenance and minor or running repairs incident to operating such rented equipment, that are not included in the rental rate are allowable.
(B) Costs incident to major repair and overhaul of rental equipment are unallowable.
(C) The allowability of charges for construction equipment rented from any division, subsidiary, or organization under common control, will be determined in accordance with 31.205-36(b)(3).
(3) Costs incurred at the job site incident to performing the work, such as the cost of superintendence, timekeeping and clerical work, engineering, utility costs, supplies, material handling, restoration and cleanup, etc., are allowable as direct or indirect costs, provided the accounting practice used is in accordance with the contractor’s established and consistently followed cost accounting practices for all work.
(4) Rental and any other costs, less any applicable credits incurred in acquiring the temporary use of land, structures, and facilities are allowable. Costs, less any applicable credits, incurred in constructing or fabricating structures and facilities of a temporary nature are allowable.
31.106 -- Facilities Contracts.
31.106-1 -- Applicable Cost Principles.
The cost principles and procedures applicable to the evaluation and determination of costs under facilities contracts (as defined in 45.301), and subcontracts thereunder, will be governed by the type of entity to which a facilities contract is awarded. Except as otherwise provided in 31.106-2 of this section, Subpart 31.2 applies to facilities contracts awarded to commercial organizations; Subpart 31.3 applies to facilities contracts awarded to educational institutions; and 31.105 applies to facilities contracts awarded to construction contractors. Whichever cost principles are appropriate will be used in the pricing of facilities contracts and contract modifications if cost analysis is performed as required by 15.404-1. In addition, the contracting officer shall incorporate the cost principles and procedures appropriate in the circumstances (e.g., Subpart 31.2; Subpart 31.3; or 31.105) by reference in facilities contracts as the basis for --
(a) Determining reimbursable costs under facilities contracts, including cost-reimbursement subcontracts thereunder;
(b) Negotiating indirect cost rates; and
(c) Determining costs of terminated contracts when the contractor elects to “voucher out” costs (see Subpart 49.3), and for settlement by determination (see 49.109-7).
31.106-2 -- Exceptions to General Rules on Allowability and Allocability.
(a) A contractor’s established accounting system and procedures are normally directed to the equitable allocation of costs to the types of products which the contractor produces or services rendered in the course of normal operating activities. The acquisition of, or work on, facilities for the Government normally does not involve the manufacturing processes, plant departmental operations, cost patterns of work, administrative and managerial control, or clerical effort usual to production of the contractor’s normal products or services.
(b) Advance agreements (see 31.109) should be made between the contractor and the contracting officer as to indirect cost items to be applied to the facilities acquisition. A contractor’s normal accounting practice for allocating indirect costs to the acquisition of contractor facilities may range from charging all these costs to this acquisition to not charging any. When necessary to produce an equitable result, the contractor’s usual method of allocating indirect cost shall be varied, and appropriate adjustment shall be made to the pools of indirect cost and the bases of their distribution.
(c) The purchase of completed facilities (or services in connection with the facilities) from outside sources does not involve the contractor’s direct labor or indirect plant maintenance personnel. Accordingly, indirect manufacturing and plant overhead costs, which are primarily incurred or generated by reason of direct labor or maintenance labor operations, are not allocable to the acquisition of such facilities.
(d) Contracts providing for the installation of new facilities or the rehabilitation of existing facilities may involve the use of the contractor’s plant maintenance labor, as distinguished from direct labor engaged in the production of the company’s normal products. In such instances, only those types of indirect manufacturing and plant operating costs that are related to or incurred by reason of the expenditures of the classes of labor used for the performance of the facilities work may be allocated to the facilities contract. Thus, a facilities contract which involves the use of plant maintenance labor only would not be subject to an allocation of such cost items as direct productive labor supervision, depreciation, and maintenance expense applicable to productive machinery and equipment, or raw material and finished goods storage costs.
(e) Where a facilities contract calls for the construction, production, or rehabilitation of equipment or other items that are involved in the regular course of the contractor’s business by the use of the contractor’s direct labor and manufacturing processes, the indirect costs normally allocated to all that work may be allocated to the facilities contract.
31.106-3 -- Contractors Commercial Items.
If facilities constituting the contractor’s usual commercial items (or only minor modifications thereof) are acquired by the Government under the contract, the Government shall not pay any amount in excess of the contractor’s most favored customer price or the price of other suppliers for like quantities of the same or substantially the same items, whichever is lower.
31.107 -- Contracts With State, Local, and Federally Recognized Indian Tribal Governments.
(a) Subpart 31.6 provides principles and standards for determining costs applicable to contracts with State, local, and federally recognized Indian tribal governments. They provide the basis for a uniform approach to the problem of determining costs and to promote efficiency and better relationships between State, local, and federally recognized Indian tribal governments, and Federal Government entities. They apply to all programs that involve contracts with State, local, and federally recognized Indian tribal governments, except contracts with --
(1) Publicly financed educational institutions subject to Subpart 31.3; or
(2) Publicly owned hospitals and other providers of medical care subject to requirements promulgated by the sponsoring Government agencies.
(b) The Office of Management and Budget will approve any other exceptions in particular cases when adequate justification is presented.
31.108 -- Contracts with Nonprofit Organizations.
Subpart 31.7 provides principles and standards for determining costs applicable to contracts with nonprofit organizations other than educational institutions, State and local governments, and those nonprofit organizations exempted under OMB Circular No. A-122.
31.109 -- Advance Agreements.
(a) The extent of allowability of the costs covered in this part applies broadly to many accounting systems in varying contract situations. Thus, the reasonableness, the allocability and the allowability under the specific cost principles at Subparts 31.2, 31.3, 31.6, and 31.7 of certain costs may be difficult to determine. To avoid possible subsequent disallowance or dispute based on unreasonableness, unallocability or unallowability under the specific cost principles at Subparts 31.2, 31.3, 31.6, and 31.7, contracting officers and contractors should seek advance agreement on the treatment of special or unusual costs. However, an advance agreement is not an absolute requirement and the absence of an advance agreement on any cost will not, in itself, affect the reasonableness, allocability or the allowability under the specific cost principles at Subparts 31.2, 31.3, 31.6, and 31.7 of that cost.
(b) Advance agreements may be negotiated either before or during a contract but should be negotiated before incurrence of the costs involved. The agreements must be in writing, executed by both contracting parties, and incorporated into applicable current and future contracts. An advance agreement shall contain a statement of its applicability and duration.
(c) The contracting officer is not authorized by this 31.109 to agree to a treatment of costs inconsistent with this part. For example, an advance agreement may not provide that, notwithstanding 31.205-20, interest is allowable.
(d) Advance agreements may be negotiated with a particular contractor for a single contract, a group of contracts, or all the contracts of a contracting office, an agency, or several agencies.
(e) The cognizant administrative contracting officer (ACO), or other contracting officer established in Part 42, shall negotiate advance agreements except that an advance agreement affecting only one contract, or class of contracts from a single contracting office, shall be negotiated by a contracting officer in the contracting office, or an ACO when delegated by the contracting officer. When the negotiation authority is delegated, the ACO shall coordinate the proposed agreement with the contracting officer before executing the advance agreement.
(f) Before negotiating an advance agreement, the Government negotiator shall --
(1) Determine if other contracting offices inside the agency or in other agencies have a significant unliquidated dollar balance in contracts with the same contractor;
(2) Inform any such office or agency of the matters under consideration for negotiation; and
(3) As appropriate, invite the office or agency and the responsible audit agency to participate in prenegotiation discussions and/or in the subsequent negotiations.
(g) Upon completion of the negotiation, the sponsor shall prepare and distribute to other interested agencies and offices, including the audit agency, copies of the executed agreement and a memorandum providing the information specified in 15.406-3, Price negotiation memorandum, as applicable.
(h) Examples of costs for which advance agreements may be particularly important are --
(1) Compensation for personal services, including but not limited to allowances for off-site pay, incentive pay, location allowances, hardship pay, cost of living differential, and termination of defined benefit pension plans;
(2) Use charges for fully depreciated assets;
(3) Deferred maintenance costs;
(4) Precontract costs;
(5) Independent research and development and bid and proposal costs;
(6) Royalties and other costs for use of patents;
(7) Selling and distribution costs;
(8) Travel and relocation costs, as related to special or mass personnel movements, as related to travel via contractor-owned, -leased, or -chartered aircraft; or as related to maximum per diem rates;
(9) Costs of idle facilities and idle capacity;
(10) Severance pay to employees on support service contracts;
(11) Plant reconversion;
(12) Professional services (e.g., legal, accounting, and engineering);
(13) General and administrative costs (e.g., corporate, division, or branch allocations) attributable to the general management, supervision, and conduct of the contractor’s business as a whole. These costs are particularly significant in construction, job-site, architect-engineer, facilities, and Government-owned contractor operated (GOCO) plant contracts (see 31.203(h));
(14) Costs of construction plant and equipment (see 31.105(d));
(15) Costs of public relations and advertising; and
(16) Training and education costs (see 31.205-44(h)).
31.110 -- Indirect Cost Rate Certification and Penalties on Unallowable Costs.
(a) Certain contracts require certification of the indirect cost rates proposed for final payment purposes. See 42.703-2 for administrative procedures regarding the certification provisions and the related contract clause prescription.
(b) If unallowable costs are included in final indirect cost settlement proposals, penalties may be assessed. See 42.709 for administrative procedures regarding the penalty assessment provisions and the related contract clause prescription.
Subpart 31.2 -- Contracts With Commercial Organizations
31.201 -- General.
31.201-1 -- Composition of Total Cost.
(a) The total cost, including standard costs properly adjusted for applicable variances, of a contract is the sum of the direct and indirect costs allocable to the contract, incurred or to be incurred, plus any allocable cost of money pursuant to 31.205-10, less any allocable credits. In ascertaining what constitutes a cost, any generally accepted method of determining or estimating costs that is equitable and is consistently applied may be used.
(b) While the total cost of a contract includes all costs properly allocable to the contract, the allowable costs to the Government are limited to those allocable costs which are allowable pursuant to Part 31 and applicable agency supplements.
31.201-2 -- Determining Allowability.
(a) A cost is allowable only when the cost complies with all of the following requirements:
(1) Reasonableness.
(2) Allocability.
(3) Standards promulgated by the CAS Board, if applicable; otherwise, generally accepted accounting principles and practices appropriate to the circumstances.
(4) Terms of the contract.
(5) Any limitations set forth in this subpart.
(b) Certain cost principles in this subpart incorporate the measurement, assignment, and allocability rules of selected CAS and limit the allowability of costs to the amounts determined using the criteria in those selected standards. Only those CAS or portions of standards specifically made applicable by the cost principles in this subpart are mandatory unless the contract is CAS-covered (see Part 30). Business units that are not otherwise subject to these standards under a CAS clause are subject to the selected standards only for the purpose of determining allowability of costs on Government contracts. Including the selected standards in the cost principles does not subject the business unit to any other CAS rules and regulations. The applicability of the CAS rules and regulations is determined by the CAS clause, if any, in the contract and the requirements of the standards themselves.
(c) When contractor accounting practices are inconsistent with this Subpart 31.2, costs resulting from such inconsistent practices in excess of the amount that would have resulted from using practices consistent with this subpart are unallowable.
(d) A contractor is responsible for accounting for costs appropriately and for maintaining records, including supporting documentation, adequate to demonstrate that costs claimed have been incurred, are allocable to the contract, and comply with applicable cost principles in this subpart and agency supplements. The contracting officer may disallow all or part of a claimed cost that is inadequately supported.
31.201-3 -- Determining Reasonableness.
(a) A cost is reasonable if, in its nature and amount, it does not exceed that which would be incurred by a prudent person in the conduct of competitive business. Reasonableness of specific costs must be examined with particular care in connection with firms or their separate divisions that may not be subject to effective competitive restraints. No presumption of reasonableness shall be attached to the incurrence of costs by a contractor. If an initial review of the facts results in a challenge of a specific cost by the contracting officer or the contracting officer’s representative, the burden of proof shall be upon the contractor to establish that such cost is reasonable.
(b) What is reasonable depends upon a variety of considerations and circumstances, including --
(1) Whether it is the type of cost generally recognized as ordinary and necessary for the conduct of the contractor’s business or the contract performance;
(2) Generally accepted sound business practices, arm’s-length bargaining, and Federal and State laws and regulations;
(3) The contractor’s responsibilities to the Government, other customers, the owners of the business, employees, and the public at large; and
(4) Any significant deviations from the contractor’s established practices.
31.201-4 -- Determining Allocability.
A cost is allocable if it is assignable or chargeable to one or more cost objectives on the basis of relative benefits received or other equitable relationship. Subject to the foregoing, a cost is allocable to a Government contract if it --
(a) Is incurred specifically for the contract;
(b) Benefits both the contract and other work, and can be distributed to them in reasonable proportion to the benefits received; or
(c) Is necessary to the overall operation of the business, although a direct relationship to any particular cost objective cannot be shown.
31.201-5 -- Credits.
The applicable portion of any income, rebate, allowance, or other credit relating to any allowable cost and received by or accruing to the contractor shall be credited to the Government either as a cost reduction or by cash refund. See 31.205-6(j)(4) for rules governing refund or credit to the Government associated with pension adjustments and asset reversions.
31.201-6 -- Accounting for Unallowable Costs.
(a) Costs that are expressly unallowable or mutually agreed to be unallowable, including mutually agreed to be unallowable directly associated costs, shall be identified and excluded from any billing, claim, or proposal applicable to a Government contract. A directly associated cost is any cost which is generated solely as a result of incurring another cost, and which would not have been incurred had the other cost not been incurred. When an unallowable cost is incurred, its directly associated costs are also unallowable.
(b) Costs which specifically become designated as unallowable or as unallowable directly associated costs of unallowable costs as a result of a written decision furnished by a contracting officer shall be identified if included in or used in computing any billing, claim, or proposal applicable to a Government contract. This identification requirement applies also to any costs incurred for the same purpose under like circumstances as the costs specifically identified as unallowable under either this paragraph or paragraph (a) above.
(c) The practices for accounting for and presentation of unallowable costs will be those as described in 48 CFR 9904.405, Accounting for Unallowable Costs.
(d) If a directly associated cost is included in a cost pool which is allocated over a base that includes the unallowable cost with which it is associated, the directly associated cost shall remain in the cost pool. Since the unallowable costs will attract their allocable share of costs from the cost pool, no further action is required to assure disallowance of the directly associated costs. In all other cases, the directly associated costs, if material in amount, must be purged from the cost pool as unallowable costs.
(e)
(1) In determining the materiality of a directly associated cost, consideration should be given to the significance of --
(i) The actual dollar amount,
(ii) The cumulative effect of all directly associated costs in a cost pool, or
(iii) The ultimate effect on the cost of Government contracts.
(2) Salary expenses of employees who participate in activities that generate unallowable costs shall be treated as directly associated costs to the extent of the time spent on the proscribed activity, provided the costs are material in accordance with subparagraph (e)(1) above (except when such salary expenses are, themselves, unallowable). The time spent in proscribed activities should be compared to total time spent on company activities to determine if the costs are material. Time spent by employees outside the normal working hours should not be considered except when it is evident that an employee engages so frequently in company activities during periods outside normal working hours as to indicate that such activities are a part of the employee’s regular duties.
(3) When a selected item of cost under 31.205 provides that directly associated costs be unallowable, it is intended that such directly associated costs be unallowable only if determined to be material in amount in accordance with the criteria provided in subparagraphs (e)(1) and (e)(2) of this section, except in those situations where allowance of any of the directly associated costs involved would be considered to be contrary to public policy.
31.201-7 -- Construction and Architect-Engineer Contracts.
Specific principles and procedures for evaluating and determining costs in connection with contracts and subcontracts for construction, and architect-engineer contracts related to construction projects, are in 31.105. The applicability of these principles and procedures is set forth in 31.000 and 31.100.
31.202 -- Direct Costs.
(a) No final cost objective shall have allocated to it as a direct cost any cost, if other costs incurred for the same purpose in like circumstances have been included in any indirect cost pool to be allocated to that or any other final cost objective. Direct costs of the contract shall be charged directly to the contract. All costs specifically identified with other final cost objectives of the contractor are direct costs of those cost objectives and are not to be charged to the contract directly or indirectly.
(b) For reasons of practicality, the contractor may treat any direct cost of a minor dollar amount as an indirect cost if the accounting treatment --
(1) Is consistently applied to all final cost objectives; and
(2) Produces substantially the same results as treating the cost as a direct cost.
31.203 -- Indirect Costs.
(a) For contracts subject to full CAS coverage, allocation of indirect costs shall be based on the applicable provisions. For all other contracts, the applicable CAS provisions in paragraphs (b) through (h) of this section apply.
(b) After direct costs have been determined and charged directly to the contract or other work, indirect costs are those remaining to be allocated to intermediate or two or more final cost objectives. No final cost objective shall have allocated to it as an indirect cost any cost, if other costs incurred for the same purpose, in like circumstances, have been included as a direct cost of that or any other final cost objective.
(c) The contractor shall accumulate indirect costs by logical cost groupings with due consideration of the reasons for incurring such costs. The contractor shall determine each grouping so as to permit use of an allocation base that is common to all cost objectives to which the grouping is to be allocated. The base selected shall allocate the grouping on the basis of the benefits accruing to intermediate and final cost objectives. When substantially the same results can be achieved through less precise methods, the number and composition of cost groupings should be governed by practical considerations and should not unduly complicate the allocation.
Class Deviation (applies to paragraph ( c ) only.
OFFICE OF THE UNDER SECRETARY OF DEFENSE
3000 DEFENSE PENTAGON
WASHINGTON, DC 20301-3000
DP (CPF) 09 SEP 2002
In reply refer to
DAR Tracking Number: 2002-O0005
MEMORANDUM FOR DIRECTORS OF DEFENSE AGENCIES
DEPUTY FOR ACQUISITION AND BUSINESS MANAGEMENT.
ASN (RD&A)/ABM
DEPUTY ASSISTANT SECRETARY OF THE AIR FORCE
(CONTRACTING), SAF/AQC
ACTING DEPUTY ASSISTANT SECRETARY OF THE ARMY
(POLICY AND PROCUREMENT). ASA(ALT)
EXECUTIVE DIRECTOR. LOGISTICS POLICY AND
ACQUISITION MANAGEMENT (DLA)
SUBJECT: Class Deviation - Federal Acquisition Regulation (FAR) 31.203(c), Indirect Costs
On September 29, 1999, the Director of Defense Procurement authorized the attached deviation from the requirements of FAR 31.203( c) when costs disallowed under FAR 31.205-52 are required to be included in the indirect cost base. The deviation expires on September 30, 2002. This memorandum extends the deviation until September 30, 2005.
Any questions concerning this memorandum should be addressed to Mr. David Capitano, Senior Procurement Analyst, at 703~602-4245 or via e-mail at:
(d) Once an appropriate base for allocating indirect costs has been accepted, the contractor shall not fragment the base by removing individual elements. All items properly includable in an indirect cost base shall bear a pro rata share of indirect costs irrespective of their acceptance as Government contract costs. For example, when a cost input base is used for the allocation of G&A costs, the contractor shall include in the base all items that would properly be part of the cost input base, whether allowable or unallowable, and these items shall bear their pro rata share of G&A costs.
(e) The method of allocating indirect costs may require revision when there is a significant change in the nature of the business, the extent of subcontracting, fixed-asset improvement programs, inventories, the volume of sales and production, manufacturing processes, the contractor’s products, or other relevant circumstances.
(f) Separate cost groupings for costs allocable to offsite locations may be necessary to permit equitable distribution of costs on the basis of the benefits accruing to the several cost objectives.
(g) A base period for allocating indirect costs is the cost accounting period during which such costs are incurred and accumulated for allocation to work performed in that period.
(1) For contracts subject to full or modified CAS coverage, the contractor shall follow the criteria and guidance in 48 CFR 9904.406 for selecting the cost accounting periods to be used in allocating indirect costs.
(2) For contracts other than those subject to paragraph (g)(1) of this section, the base period for allocating indirect costs shall be the contractor’s fiscal year used for financial reporting purposes in accordance with generally accepted accounting principles. The fiscal year will normally be 12 months, but a different period may be appropriate (e.g., when a change in fiscal year occurs due to a business combination or other circumstances).
(h) Special care should be exercised in applying the principles of paragraphs (c), (d), and (e) of this section when Government-owned contractor-operated (GOCO) plants are involved. The distribution of corporate, division or branch office G&A expenses to such plants operating with little or no dependence on corporate administrative activities may require more precise cost groupings, detailed accounts screening, and carefully developed distribution bases.
31.204 -- Application of Principles and Procedures.
(a) Costs are allowable to the extent they are reasonable, allocable, and determined to be allowable under 31.201, 31.202, 31.203, and 31.205. These criteria apply to all of the selected items that follow, even if particular guidance is provided for certain items for emphasis or clarity.
(b)
(1) For the following subcontract types, costs incurred as reimbursement or payments to a subcontractor are allowable to the extent the reimbursements or payments are for costs incurred by the subcontractor that are consistent with this part:
(i) Costs-reimbursement.
(ii) Fixed-price incentive.
(iii) Price redeterminable (i.e., firm-fixed-price contracts with prospective price redetermination and fixed ceiling-price contracts with retroactive price redetermination).
(2) The requirements of paragraph (b)(1) of this section apply to any tier above the first firm-fixed-price subcontract or fixed-price subcontract with economic price adjustment provisions.
(c) Costs incurred as payments under firm-fixed-price subcontracts or fixed-price subcontracts with economic price adjustment provisions or modifications thereto, for which subcontract cost analysis was performed are allowable if the price was negotiated in accordance with 31.102.
(d) Section 31.205 does not cover every element of cost. Failure to include any item of cost does not imply that it is either allowable or unallowable. The determination of allowability shall be based on the principles and standards in this subpart and the treatment of similar or related selected items. When more than one subsection in 31.205 is relevant to a contractor cost, the cost shall be apportioned among the applicable subsections, and the determination of allowability of each portion shall be based on the guidance contained in the applicable subsection. When a cost, to which more than one subsection in 31.205 is relevant, cannot be apportioned, the determination of allowability shall be based on the guidance contained in the subsection that most specifically deals with, or best captures the essential nature of, the cost at issue.
31.205 -- Selected Costs.
31.205-1 -- Public Relations and Advertising Costs.
(a) “Public relations” means all functions and activities dedicated to --
(1) Maintaining, protecting, and enhancing the image of a concern or its products; or
(2) Maintaining or promoting reciprocal understanding and favorable relations with the public at large, or any segment of the public. The term public relations includes activities associated with areas such as advertising, customer relations, etc.
(b) “Advertising” means the use of media to promote the sale of products or services and to accomplish the activities referred to in paragraph (d) of this subsection, regardless of the medium employed, when the advertiser has control over the form and content of what will appear, the media in which it will appear, and when it will appear. Advertising media include but are not limited to conventions, exhibits, free goods, samples, magazines, newspapers, trade papers, direct mail, dealer cards, window displays, outdoor advertising, radio, and television.
(c) Public relations and advertising costs include the costs of media time and space, purchased services performed by outside organizations, as well as the applicable portion of salaries, travel, and fringe benefits of employees engaged in the functions and activities identified in paragraphs (a) and (b) of this subsection.
(d) The only allowable advertising costs are those that are --
(1) Specifically required by contract, or that arise from requirements of Government contracts and that are exclusively for –
(i) Acquiring scarce items for contract performance; or
(ii) Disposing of scrap or surplus materials acquired for contract performance.
(2) Costs of activities to promote sales of products normally sold to the U.S. Government, including trade shows, which contain a significant effort to promote exports from the United States. Such costs are allowable, notwithstanding paragraphs (f)(1), (f)(3), (f)(4)(ii), and (f)(5) of this subsection. However, such costs do not include the costs of memorabilia (e.g., models, gifts, and souvenirs), alcoholic beverages, entertainment, and physical facilities that are primarily used for entertainment rather than product promotion; or
(3) Allowable in accordance with 31.205-34.
(e) Allowable public relations costs include the following:
(1) Costs specifically required by contract.
(2) Costs of --
(i) Responding to inquiries on company policies and activities;
(ii) Communicating with the public, press, stockholders, creditors, and customers; and
(iii) Conducting general liaison with news media and Government public relations officers, to the extent that such activities are limited to communication and liaison necessary to keep the public informed on matters of public concern such as notice of contract awards, plant closings or openings, employee layoffs or rehires, financial information, etc.
(3) Costs of participation in community service activities (e.g., blood bank drives, charity drives, savings bond drives, disaster assistance, etc.).
(4) Costs of plant tours and open houses (but see subparagraph (f)(5) of this subsection).
(5) Costs of keel laying, ship launching, commissioning, and roll-out ceremonies, to the extent specifically provided for by contract.
(f) Unallowable public relations and advertising costs include the following:
(1) All public relations and advertising costs, other than those specified in paragraphs (d) and (e) of this subsection, whose primary purpose is to promote the sale of products or services by stimulating interest in a product or product line (except for those costs made allowable under 31.205-38(b)(5)), or by disseminating messages calling favorable attention to the contractor for purposes of enhancing the company image to sell the company’s products or services.
(2) All costs of trade shows and other special events which do not contain a significant effort to promote the export sales of products normally sold to the U.S. Government.
(3) Costs of sponsoring meetings, conventions, symposia, seminars, and other special events when the principal purpose of the event is other than dissemination of technical information or stimulation of production.
(4) Costs of ceremonies such as --
(i) Corporate celebrations and
(ii) New product announcements.
(5) Costs of promotional material, motion pictures, videotapes, brochures, handouts, magazines, and other media that are designed to call favorable attention to the contractor and its activities.
(6) Costs of souvenirs, models, imprinted clothing, buttons, and other mementos provided to customers or the public.
(7) Costs of memberships in civic and community organizations.
31.205-2 -- [Reserved]
31.205-3 -- Bad Debts.
Bad debts, including actual or estimated losses arising from uncollectible accounts receivable due from customers and other claims, and any directly associated costs such as collection costs, and legal costs are unallowable.
31.205-4 -- Bonding Costs.
(a) Bonding costs arise when the Government requires assurance against financial loss to itself or others by reason of the act or default of the contractor. They arise also in instances where the contractor requires similar assurance. Included are such bonds as bid, performance, payment, advance payment, infringement, and fidelity bonds.
(b) Costs of bonding required pursuant to the terms of the contract are allowable.
(c) Costs of bonding required by the contractor in the general conduct of its business are allowable to the extent that such bonding is in accordance with sound business practice and the rates and premiums are reasonable under the circumstances.
31.205-5 – [Reserved].
31.205-6 -- Compensation for Personal Services.
(a) General. Compensation for personal services is allowable subject to the following general criteria and additional requirements contained in other parts of this cost principle:
(1) Compensation for personal services must be for work performed by the employee in the current year and must not represent a retroactive adjustment of prior years’ salaries or wages (but see paragraphs (g), (h), (j), (k), (m), and (o) of this subsection).
(2) The total compensation for individual employees or job classes of employees must be reasonable for the work performed; however, specific restrictions on individual compensation elements apply when prescribed.
(3) The compensation must be based upon and conform to the terms and conditions of the contractor’s established compensation plan or practice followed so consistently as to imply, in effect, an agreement to make the payment.
(4) No presumption of allowability will exist where the contractor introduces major revisions of existing compensation plans or new plans and the contractor has not provided the cognizant ACO, either before implementation or within a reasonable period after it, an opportunity to review the allowability of the changes.
(5) Costs that are unallowable under other paragraphs of this Subpart 31.2 are not allowable under this subsection 31.205-6 solely on the basis that they constitute compensation for personal services.
(6)
(i) Compensation costs for certain individuals give rise to the need for special consideration. Such individuals include:
(A) Owners of closely held corporations, members of limited liability companies, partners, sole proprietors, or members of their immediate families; and
(B) Persons who are contractually committed to acquire a substantial financial interest in the contractor’s enterprise.
(ii) For these individuals, compensation must—
(A) Be reasonable for the personal services rendered; and
(B) Not be a distribution of profits (which is not an allowable contract cost).
(iii) For owners of closely held companies, compensation in excess of the costs that are deductible as compensation under the Internal Revenue Code (26 U.S.C.) and regulations under it is unallowable.
(b) Reasonableness—
(1) Compensation pursuant to labor-management agreements. If costs of compensation established under “arm’s length” labor-management agreements negotiated under the terms of the Federal Labor Relations Act or similar state statues are otherwise allowable, the costs are reasonable unless, as applied to work in performing Government contracts, the costs are unwarranted by the character and circumstances of the work or discriminatory against the Government. The application of the provisions of a labor-management agreement designed to apply to a given set of circumstances and conditions of employment (e.g., work involving extremely hazardous activities or work not requiring recurrent use of overtime) is unwarranted when applied to a Government contract involving significantly different circumstances and conditions of employment (e.g., work involving less hazardous activities or work continually requiring use of overtime). It is discriminatory against the Government if it results in employee compensation (in whatever form or name) in excess of that being paid for similar non-Government work under comparable circumstances.
(2) Compensation not covered by labor-management agreements. Compensation for each employee or job class of employees must be reasonable for the work performed. Compensation is reasonable if the aggregate of each measurable and allowable element sums to a reasonable total. In determining the reasonableness of total compensation, consider only allowable individual elements of compensation. In addition to the provisions of 31.201-3, in testing the reasonableness of compensation for particular employees or job classes of employees, consider factors determined to be relevant by the contracting officer. Factors that may be relevant include, but are not limited to, conformity with compensation practices of other firms—
(i) Of the same size;
(ii) In the same industry;
(iii) In the same geographic area; and
(iv) Engaged in similar non-government work under comparable circumstances.
(c) [Reserved]
(d) Form of payment.
(1) Compensation for personal services includes compensation paid or to be paid in the future to employees in the form of—
(i) Cash;
(ii) Corporate securities, such as stocks, bonds, and other financial instruments (see paragraph (d)(2) of this subsection regarding valuation); or
(iii) Other assets, products, or services.
(2) When compensation is paid with securities of the contractor or of an affiliate, the following additional restrictions apply:
(i) Valuation placed on the securities shall be the fair market value on the first date the number of shares awarded is known, determined upon the most objective basis available.
(ii) Accruals for the cost of securities before issuing the securities to the employees are subject to adjustment according to the possibilities that the employees will not receive the securities and that their interest in the accruals will be forfeited.
(e) Income tax differential pay.
(1) Differential allowances for additional income taxes resulting from foreign assignments are allowable.
(2) Differential allowances for additional income taxes resulting from domestic assignments are unallowable. (However, payments for increased employee income or Federal Insurance Contributions Act taxes incident to allowable reimbursed relocation costs are allowable under 31.205-35(a)(10).)
(f) Bonuses and incentive compensation.
(1) Bonuses, and incentive compensation are allowable provided the—
(i) Awards are paid or accrued under an agreement entered into in good faith between the contractor and the employees before the services are rendered or pursuant to an established plan or policy followed by the contractor so consistently as to imply, in effect, an agreement to make such payment; and
(ii) Basis for the award is supported.
(2) When the bonus and incentive compensation payments are deferred, the costs are subject to the requirements of paragraphs (f)(1) and (k) of this subsection.
(g) Severance pay.
(1) Severance pay is a payment in addition to regular salaries and wages by contractors to workers whose employment is being involuntarily terminated. Payments for early retirement incentive plans are covered in subparagraph (j)(6) of this subsection.
(2) Severance pay is allowable only to the extent that, in each case, it is required by—
(i) Law
(ii) Employer-employee agreement.
(iii) Established policy that constitutes, in effect, an implied agreement on the contractor's part; or
(iv) Circumstances of the particular employment.
(3) Payments made in the event of employment with a replacement contractor where continuity of employment with credit for prior length of service is preserved under substantially equal conditions of employment, or continued employment by the contractor at another facility, subsidiary, affiliate, or parent company of the contractor are not severance pay and are unallowable.
(4) Actual normal turnover severance payments shall be allocated to all work performed in the contractor’s plant. However, if the contractor uses the accrual method to account for normal turnover severance payments, that method will be acceptable if the amount of the accrual is—
(i) Reasonable in light of payments actually made for normal severances over a representative past period; and
(ii) Allocated to all work performed in the contractor’s plant.
(5) Abnormal or mass severance pay is of such a conjectural nature that accruals for this purpose are not allowable. However, the Government recognizes its obligation to participate, to the extent of its fair share, in any specific payment. Thus, the government will consider allowability on a case-by-case basis.
(6) Under 10 U.S.C 2324(e)(1)(M) and 41 U.S.C. 256(e)(1)(M), the costs of severance payments to foreign nationals employed under a service contract performed outside the United States are unallowable to the extent that such payments exceed amounts typically paid to employees providing similar services in the same industry in the United States. Further, under 10 U.S.C 2324(e)(1)(N) and 41 U.S.C. 256(e)(1)(N), all such costs of severance payments that are otherwise allowable are unallowable if the termination of employment of foreign national is the result of the closing of, or the curtailment of activities at, a United States facility in that country at the request of the government of that country; this does not apply if the closing of a facility or curtailment of activities is made pursuant to a status-of-forces or other country-to-country agreement entered into with the government of that country before November 29, 1989. 10 U.S.C 2324(e)(3) and 41 U.S.C. 256(e)(2) permit the head of the agency to waive these cost allowability limitations under certain circumstances (see 37.113 and the solicitation provision at 52.237-8).
(h) Backpay. Backpay is a retroactive adjustment of prior years’ salaries or wages. Backpay is unallowable except as follows:
(1) Payments to employees resulting from underpaid work actually performed are allowable, if required by a negotiated settlement, order, or court decree.
(2) Payments to union employees for the difference in their past and current wage rates for working without a contract or labor agreement during labor management negotiation are allowable:
(3) Payments to nonunion employees based upon results of union agreement negotiation are allowable only if--
(i) A formal agreement or understanding exists between management and the employees concerning these payments, or
(ii) An established policy or practice exists and is followed by the contractor so consistently as to imply, in effect, an agreement to make such payments.
(i) Compensation based on changes in the prices of corporate securities or corporate security ownership, such as stock options, stock appreciation rights, phantom stock plans, and junior stock conversions.
(1) Any compensation which is calculated, or valued, based on changes in the price of corporate securities is unallowable.
(2) Any compensation represented by dividend payments or which is calculated based on dividend payments is unallowable.
(3) If a contractor pays an employee in lieu of the employee receiving or exercising a right, option, or benefit which would have been unallowable under this paragraph (i), such payments are also unallowable.
(j) Pension costs.
(1) Pension plans are normally segregated into two types of plans: defined-benefit and defined-contribution pension plans. The contractor shall measure, assign, and allocate the costs of all defined-benefit pension plans and the costs of all defined-contribution pension plans in compliance with 48 CFR 9904.412—Cost Accounting Standard for Composition and Measurement of Pension Cost, and 48 CFR 9904.413—Adjustment and Allocation of Pension Cost. Pension costs are allowable subject to the referenced standards and the cost limitations and exclusions set forth in paragraph (j)(1)(i) and in paragraphs (j)(2) through (j)(6) of this subsection.
(i) Except for nonqualified pension plans using the pay-as-you-go cost method, to be allowable in the current year, the contractor shall fund pension costs by the time set for filing of the Federal income tax return or any extension. Pension costs assigned to the current year, but not funded by the tax return time, are not be allowable in any subsequent year. For nonqualified pension plans using the pay-as-you-go method, to be allowable in the current year, the contractor shall allocate pension costs in the cost accounting period that the pension costs are assigned.
(ii) Pension payments must be paid pursuant to an agreement entered into in good faith between the contractor and employees before the work or services are performed and to the terms and conditions of the established plan. The cost of changes in pension plans are not allowable if the changes are discriminatory to the Government or are not intended to be applied consistently for all employees under similar circumstances in the future.
(iii) Except as provided for early retirement benefits in subparagraph (j)(6) of this subsection, one-time-only pension supplements not available to all participants of the basic plan are not allowable as pension costs, unless the supplemental benefits represent a separate pension plan and the benefits are payable for life at the option of the employee.
(iv) Increases in payments to previously retired plan participants covering cost-of-living adjustments are allowable if paid in accordance with a policy or practice consistently followed.
(2) Defined- benefit pension plans. The cost limitations and exclusions pertaining to defined-benefit plans are as follows:
(i)
(A) Except for nonqualified pension plans, pension costs (see 48 CFR 9904.412-40(a)(1)) assigned to the current accounting period, but not funded during it, are not allowable in subsequent years (except that a payment made to a fund by the time set for filing the Federal income tax return or any extension thereof is considered to have been made during such taxable year). However, any portion of pension cost computed for a cost accounting period, that exceeds the amount required to be funded pursuant to a waiver granted under the provisions of the Employee Retirement Income Security Act of 1974 (ERISA), will be allowable in those future accounting periods in which the funding of such excess amounts occurs (see 48 CFR 9904.412-50(c)(5)).
(B) For nonqualified pension plans, except those using the pay-as-you-go cost method, allowable costs are limited to the amount allocable in accordance with 48 CFR 9904.412-50(d)(2).
(C) For nonqualified pension plans using the pay-as-you-go cost method, allowable costs are limited to the amounts allocable in accordance with 48 CFR 9904.412-50(d)(3).
(ii) Any amount funded in excess of the pension cost assigned to a cost accounting period is not allowable and shall be accounted for as set forth at 48 CFR 9904.412-50(a)(4). The excess amount is allowable in the future period to which it is assigned, to the extent it is not otherwise unallowable.
(iii) Increased pension costs are unallowable if the increase is caused by a delay in funding beyond 30 days after each quarter of the year to which they are assignable. If a composite rate is used for allocating pension costs between the segments of a company and if, because of differences in the timing of the funding by the segments, an inequity exists, allowable pension costs for each segment will be limited to that particular segment’s calculation of pension costs as provided for in 48 CFR 9904.413-50(c). The contractor shall make determinations of unallowable costs in accordance with the actuarial method used in calculating pension costs.
(iv) The contracting officer will consider the allowability of the cost of indemnifying the Pension Benefit Guaranty Corporation (PBGC) under ERISA Section 4062 or 4064 arising from terminating an employee deferred compensation plan on a case-by-case basis; provided that if insurance was required by the PBGC under ERISA section 4023, it was so obtained and the indemnification payment is not recoverable under the insurance. Consideration under the foregoing circumstances will be primarily for the purpose of appraising the extent to which the indemnification payment is allocable to Government work. If a beneficial or other equitable relationship exists, the Government will participate, despite the requirements of 31.205-19(c)(3) and (d)(3), in the indemnification payment to the extent of its fair share.
(v) Increased pension costs resulting from the withdrawal of assets from a pension fund and transfer to another employee benefit plan fund, or transfer of assets to another account within the same fund, are unallowable except to the extent authorized by an advance agreement. If the withdrawal of assets from a pension fund is a plan termination under ERISA, the provisions of paragraph (j)(3) of this subsection apply. The advance agreement shall--
(A) State the amount of the Government’s equitable share in the gross amount withdrawn or transferred; and
(B) Provide that the Government receives a credit equal to the amount of the Government’s equitable share of the gross withdrawal or transfer.
(3) Pension adjustments and asset reversions.
(i) For segment closings, pension plan terminations, or curtailment of benefits, the amount adjustment shall be—
(A) For contracts and subcontracts that are subject to full coverage under the Cost Accounting Standards (CAS) Board rules and regulations, the amount measured, assigned, and allocated in accordance with 48 CFR 9904.413-50(c)(12); and
(B) For contracts and subcontracts that are not subject to full coverage under the CAS, the amount measured, assigned, and allocated in accordance with 48 CFR 9904.413-50(c)(12), except the numerator of the fraction at at 48 CFR 9904.413-50(c)(12)(vi) is the sum of the pension plan costs allocated to all non-CAS-covered contracts and subcontracts that are subject to Subpart 31.2 or for which cost or pricing data were submitted.
(ii) For all other situations where assets revert to the contractor, or such assets are constructively received by it for any reason, the contractor shall, at the Government’s option, make a refund or give a credit to the Government for its equitable share of the gross amount withdrawn. The Government’s equitable share shall reflect the Government’s participation in pension costs through those contracts for which cost or pricing data were submitted or that are subject to Subpart 31.2. Excise taxes on pension plan asset reversions or withdrawals under this paragraph (j)(3)(ii) are unallowable in accordance with 31.205-41(b)(6).
(4) Defined-contribution pension plans. In addition to defined-contribution pension plans, this paragraph also covers profit sharing, savings plans, and other such plans, provided the plans fall within the definition of a pension plan at 31.001.
(i) Allowable pension cost is limited to the net contribution required to be made for a cost accounting period after taking into account dividends and other credits, where applicable. However, any portion of pension cost computed for a cost accounting period that exceeds the amount required to be funded pursuant to a waiver granted under the provisions of ERISA will be allowable in those future accounting periods in which the funding of such excess amounts occurs (see 48 CFR 9904.412-50(c)(5)).
(ii) The provisions of paragraphs (j)(2)(ii) and (iv) of this subsection apply to defined-contribution plans.
(5) Pension plans using the pay-as-you-go cost method. When using the pay-as-you-go cost method, the contractor shall measure, assign, and allocate the cost of pension plans in accordance with 48 CFR 9904.412 and 9904.413. Pension costs for a pension plan using the pay-as-you-go cost method are allowable to the extent they are not otherwise unallowable.
(6) Early retirement incentives. An early retirement incentive plan is an incentive given to an employee to retire early. For contract costing purposes, costs of early retirement incentives are allowable subject to the pension cost criteria in contained in paragraphs (j)(2)(i) through (iv) of this subsection provided--
(i) The contractor measures, assigns, and allocates the costs in accordance with the contractor’s accounting practices for pension costs;
(ii) The incentives are in accordance with the terms and conditions of an early retirement incentive plan;
(iii) The contractor applies the plan only to active employees. The cost of extending the plan to employees who retired or were terminated before the adoption of the plan is unallowable; and
(iv) The present value of the total incentives given to any employee in excess of the amount of the employee’s annual salary for the previous fiscal year before the employee’s retirement is unallowable. The contractor shall compute the present value in accordance with its accounting practices for pension costs. The contractor shall account for any unallowable costs in accordance with 48 CFR 9904.412-50(a)(2).
(k) Deferred compensation other than pensions. The costs of deferred compensation awards are allowable subject to the following limitations:
(1) The costs shall be measured, assigned and allocated in accordance with 48 CFR 9904.415, Accounting for the Cost of Deferred Compensation.
(2) The costs of deferred compensation awards are unallowable if the awards are made in periods subsequent to the period when the work being remunerated was performed.
(l) Compensation incidental to business acquisitions. The following costs are unallowable:
(1) Payments to employees under agreements in which they receive special compensation, in excess of the contractor’s normal severance pay practice, if their employment terminates following a change in the management control over, or ownership of, the contractor or a substantial portion of its assets.
(2) Payments to employees under plans introduced in connection with a change (whether actual or prospective) in the management control over, or ownership of, the contractor or a substantial portion of its assets in which those employees receive special compensation, which is contingent upon the employee remaining with the contractor for a specified period of time.
(m) Fringe benefits.
(1) Fringe benefits are allowances and services provided by the contractor to its employees as compensation in addition to regular wages and salaries. Fringe benefits include, but are not limited to, the cost of vacations, sick leave, holidays, military leave, employee insurance, and supplemental unemployment benefit plans. Except as provided otherwise in Subpart 31.2, the costs of fringe benefits are allowable to the extent that they are reasonable and are required by law, employer-employee agreement, or an established policy of the contractor.
(2) That portion of the cost of company-furnished automobiles that relates to personal use by employees (including transportation to and from work) is unallowable regardless of whether the cost is reported as taxable income to the employees (see 31.205-46(d)).
(n) Employee rebate and purchase discount plans. Rebates and purchase discounts, in whatever form, granted to employees on products or services produced by the contractor or affiliates are unallowable.
(o) Postretirement benefits other than pensions (PRB).
(1) PRB covers all benefits, other than cash benefits and life insurance benefits paid by pension plans, provided to employees, their beneficiaries, and covered dependents during the period following the employees’ retirement. Benefits encompassed include, but are not limited to, postretirement health care; life insurance provided outside a pension plan; and other welfare benefits such as tuition assistance, day care, legal services, and housing subsidies provided after retirement.
(2) To be allowable, PRB costs shall be incurred pursuant to law, employer-employee agreement, or an established policy of the contractor, and shall comply with paragraphs (o)(2)(i), (ii), or (iii) of this subsection.
(i) Pay-as-you-go. PRB costs are not accrued during the working lives of employees. Costs are assigned to the period in which—
(A) Benefits are actually provided; or
(B) The costs are paid to an insurer, provider, or other recipient for current year benefits or premiums.
(ii) Terminal funding. PRB costs are not accrued during the working lives of the employees.
(A) Terminal funding occurs when the entire PRB liability is paid in a lump sum upon the termination of employees (or upon conversion to such a terminal-funded plan) to an insurer or trustee to establish and maintain a fund or reserve for the sole purpose of providing PRB to retirees.
(B) Terminal funded costs shall be amortized over a period of 15 years.
(iii) Accrual basis. PRB costs are accrued during the working lives of employees. Accrued PRB costs shall be—
(A) Measured and assigned in accordance with generally accepted accounting principles. However, the portion of the PRB costs attributable to the transition obligation assigned to the current year that is in excess of the amount assignable under the delayed recognition methodology described in paragraphs 112 and 113 of Financial Accounting Standards Board Statement 106 is unallowable. The transition obligation is defined in Statement 106, paragraph 110;
(B) Paid to an insurer or trustee to establish and maintain a fund or reserve for the sole purpose of providing PRB to retirees; and
(C) Calculated in accordance with generally accepted actuarial principles and practices as promulgated by the Actuarial Standards Board.
(3) To be allowable, costs must be funded by the time set for filing the Federal income tax return or any extension thereof, or paid to an insurer, provider, or other recipient by the time set for filing the Federal income tax return or extension thereof. PRB costs assigned to the current year, but not funded, paid or otherwise liquidated by the tax return due date as extended are not allowable in any subsequent year.
(4) Increased PRB costs caused by delay in funding beyond 30 days after each quarter of the year to which they are assignable are unallowable.
(5) The Government shall receive an equitable share of any amount of previously funded PRB costs which revert or inure to the contractor. Such equitable share shall reflect the Government’s previous participation in PRB costs through those contracts for which cost or pricing data were required or which were subject to Subpart 31.2.
(p) Limitation on allowability of compensation for certain contractor personnel.
(1) Costs incurred after January 1, 1998, for compensation of a senior executive in excess of the benchmark compensation amount determined applicable for the contractor fiscal year by the Administrator, Office of Federal Procurement Policy (OFPP), under Section 39 of the OFPP Act (41 U.S.C. 435) are unallowable (10 U.S.C. 2324(e)(1)(P) and 41 U.S.C. 256(e)(1)(P)). This limitation is the sole statutory limitation on allowable senior executive compensation costs incurred after January 1, 1998, under new or previously existing contracts. This limitation applies whether or not the affected contracts were previously subject to a statutory limitation on such costs. (Note that pursuant to Section 804 of Pub. L. 105-261, the definition of “senior executive in (p)(2)(ii) has been changed for compensation costs incurred after January 1, 1999.)
(2) As used in this paragraph--
(i) “Compensation” means the total amount of wages, salary, bonuses, deferred compensation (see paragraph (k) of this subsection), and employer contributions to defined contribution pension plans (see paragraphs (j)(4) and (q) of this subsection), for the fiscal year, whether paid, earned, or otherwise accruing, as recorded in the contractor’s cost accounting records for the fiscal year.
(ii) “Senior executive” means --
(A) Prior to January 2, 1999--
(1) The Chief Executive Officer (CEO) or any individual acting in a similar capacity at the contractor’s headquarters;
(2) The four most highly compensated employees in management positions at the contractor’s headquarters, other than the CEO; and
(3) If the contractor has intermediate home offices or segments that report directly to the contractor’s headquarters, the five most highly compensated employees in management positions at each such intermediate home office or segment.
(B) Effective January 2, 1999, the five most highly compensated employees in management positions at each home office and each segment of the contractor, whether or not the home office or segment reports directly to the contractor’s headquarters.
(iii) “Fiscal year” means the fiscal year established by the contractor for accounting purposes.
(iv) “Contractor’s headquarters” means the highest organizational level from which executive compensation costs are allocated to Government contracts.
(q) Employee stock ownership plans (ESOP).
(1) An ESOP is a stock bonus plan designed to invest primarily in the stock of the employer corporation. The contractor’s contributions to an Employee Stock Ownership Trust (ESOT) may be in the form of cash, stock, or property.
(2) Costs of ESOP’s are allowable subject to the following conditions:
(i) For ESOPs that meet the definition of a pension plan at 31.001, the contractor—
(A) Measures, assigns, and allocates the costs in accordance with 48 CFR 9904.412;
(B) Funds the pension costs by the time set for filing of the Federal income tax return or any extension. Pension costs assigned to the current year, but not funded by the tax return time, are not allowable in any subsequent year; and
(C) Meets the requirements of paragraph (j)(2)(ii) of this subsection.
(ii) For ESOPs that do not meet the definition of a pension plan at 31.001, the contractor measures, assigns, and allocates costs in accordance with 48 CFR 9904.415.
(iii) Contributions by the contractor in any one year that exceed the deductibility limits of the Internal Revenue Code for that year are unallowable.
(iv) When the contribution is in the form of stock, the value of the stock contribution is limited to the fair market value of the stock on the date that title is effectively transferred to the trust.
(v) When the contribution is in the form of cash—
(A) Stock purchases by the ESOT in excess of fair market value are unallowable; and
(B) When stock purchases are in excess of fair market value, the contractor shall credit the amount of the excess to the same indirect cost pools that were charged for the ESOP contributions in the year in which the stock purchase occurs. However, when the trust purchases the stock with borrowed funds which will be repaid over a period of years by cash contributions from the contractor to the trust, the contractor shall credit the excess price over fair market value to the indirect cost pools pro rata over the period of years during which the contractor contributes the cash used by the trust to repay the loan.
(vi) When the fair market value of unissued stock or stock of a closely held corporation is not readily determinable, the valuation will be made on a case-by-case basis taking into consideration the guidelines for valuation used by the IRS.
31.205-7 -- Contingencies.
(a) “Contingency,” as used in this subpart, means a possible future event or condition arising from presently known or unknown causes, the outcome of which is indeterminable at the present time.
(b) Costs for contingencies are generally unallowable for historical costing purposes because such costing deals with costs incurred and recorded on the contractor’s books. However, in some cases, as for example, terminations, a contingency factor may be recognized when it is applicable to a past period to give recognition to minor unsettled factors in the interest of expediting settlement.
(c) In connection with estimates of future costs, contingencies fall into two categories:
(1) Those that may arise from presently known and existing conditions, the effects of which are foreseeable within reasonable limits of accuracy; e.g., anticipated costs of rejects and defective work. Contingencies of this category are to be included in the estimates of future costs so as to provide the best estimate of performance cost.
(2) Those that may arise from presently known or unknown conditions, the effect of which cannot be measured so precisely as to provide equitable results to the contractor and to the Government; e.g., results of pending litigation. Contingencies of this category are to be excluded from cost estimates under the several items of cost, but should be disclosed separately (including the basis upon which the contingency is computed) to facilitate the negotiation of appropriate contractual coverage. (See, for example, 31.205-6(g), and 31.205-19.)
31.205-8 -- Contributions or Donations.
Contributions or donations, including cash, property and services, regardless of recipient, are unallowable, except as provided in 31.205-1(e)(3).
31.205-9 -- [Reserved]
31.205-10 -- Cost of Money.
(a) General. Cost of money--
(1) Is an imputed cost that is not a form of interest on borrowings (see 31.205-20);
(2) Is an “incurred cost” for cost-reimbursement purposes under applicable cost-reimbursement contracts and for progress payment purposes under fixed-price contracts; and
(3) Refers to—
(i) Facilities capital cost of money (48 CFR 9904.414): and
(ii) Cost of money as an element of the cost of capital assets under construction (48 CFR 9904.417).
(b) Cost of money is allowable, provided--
(1) It is measured, assigned, and allocated to contracts in accordance with 48 CFR 9904.414 or measured and added to the cost of capital assets under construction in accordance with 48 CFR 9904.417, as applicable;
(2) The requirements of 31.205-52, which limit the allowability of cost of money, are followed; and
(3) The estimated facilities capital cost of money is specifically identified and proposed in cost proposals relating to the contract under which the cost is to be claimed.
(c) Actual interest cost in lieu of the calculated imputed cost of money is unallowable.
31.205-11 -- Depreciation.
(a) Depreciation on a contractor’s plant, equipment, and other capital facilities is an allowable contract cost, subject to the limitations contained in this cost principle. For tangible personal property, only estimated residual values that exceed 10 percent of the capitalized cost of the asset need be used in establishing depreciable c