Additional Equipment Costs
A contractor is also entitled to recover additional equipment costs over an extended contract period where the government requires the use of that equipment beyond the original contract period. Community Heating & Plumbina Co.. Inc. v. Kelso, 987 F.2d 1575, 1581 (Fed. Cir. 1993), citing Nolan Bros. v. United States, 437 F.2d 1371 (Ct. C1. 1971); Smith-Cothran, Inc., DOTCAB Nos. 1931 et al., 89-1 BCA 21,554 (1989).